- Home
- JAL JEEVAN MISSION 2021-22 - Phase I -Au...
JAL JEEVAN MISSION 2021-22 - Phase I -Augmentation of Water supply schemes to Kottamkara Grama Panchayath in Kollam
Project |
JAL JEEVAN MISSION 2021-22 - Phase I -Augmentation of Water supply schemes to Kottamkara Grama Panchayath in Kollam |
Project Code |
KLMJJM082010727 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JAL JEEVAN MISSION 2021-22 - Phase -Augmentation of Water supply schemes to Kottamkara Grama Panchayath |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam PH Dn |
AS Amount (Rs) |
490700000
|
AS Number |
GO(Rt.) No.541/2020/WRD |
TS Amount (Rs) |
382861000 |
TS Number |
1443/2021-22 |
Total Bill Submitted (Rs) |
67825276 |
Total Bill Paid (Rs) |
67825276 |
Population Benefitted |
12000 |
Capacity in MLD |
0.13 |
Actual Project Completion Date |
18 Sep 2023 |
Coverage |
Kottankara Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JAL JEEVAN MISSION 2021-22 - Phase I -Augmentation of Water supply schemes to Kottamkara Grama Panchayath in Kollam |
Kollam WS Sn 3 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
3LL OHSR at Mampuzha - Floor Slab of tank ,Walkway concrete work completed |
Kollam PH Dn EE |
|
22 Jun 2024 |
3LL OHSR at Mampuzha - Floor Slab of tank ,Walkway concrete work completed. |
Kollam WS Sn 3 - AE |
|
19 Jun 2024 |
3LL OHSR at Mampuzha - Floor Slab of tank ,Walkway concrete work completed. |
Kollam WS Sn 3 - AE |
|
18 Jun 2024 |
3LL OHSR at Mampuzha - Floor Slab Shuttering work in progress |
Kollam WS Sn 3 - AE |
|
14 Jun 2024 |
Set out of 8.5LL OHSR at Mekkone started. |
Kollam WS Sn 3 - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/03/2022 |
Scheduled date of Completion of the Project |
18 Sep 2023 |
Expected date of Completion |
30/09/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
02 Dec 2021 |