Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Jan 2024 | Progress of work is very slow. | Kollam WS Sn 3 - AE | |
17 Jan 2024 | Progress of work is very slow. | Kollam WS Sn 3 - AE | |
12 Jan 2024 | 3LL OHSR - floor slab reinforcement work in progress | Kollam WS Sn 3 - AE | |
09 Jan 2024 | 3LL OHSR - floor beam reinforcement work in progress | Kollam WS Sn 3 - AE | |
06 Jan 2024 | Progress of work is very slow. | Kollam WS Sn 3 - AE | |
05 Jan 2024 | 400mm DI pipe laying work in progress. | Kollam WS Sn 3 - AE | |
03 Jan 2024 | 400mm DI pipe laying work in progress. | Kollam WS Sn 3 - AE | |
30 Dec 2023 | 400mm DI pipe laying work in progress. | Kollam WS Sn 3 - AE | |
28 Dec 2023 | 400mm DI pipe laying work in progress. | Kollam WS Sn 3 - AE | |
26 Dec 2023 | 400mm DI pipe laying work in progress, 3LL OHSR - Fourth stage of column concrete completed. | Kollam WS Sn 3 - AE |