Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jul 2023 | 200mm DI Pipe laying work in progress. | Kollam WS Sn 3 - AE | |
24 Jul 2023 | 125 mm HDPE pipe laying work at NH 208 Kerlapuram to Karikkode work in progress. | Kollam WS Sn 3 - AE | |
19 Jul 2023 | 125mm HDPE pipe laying work at NH 208 Kerlapuram to Karikkode work in progress. | Kollam WS Sn 3 - AE | |
15 Jul 2023 | DI interconncetion and 125mm HDPE pipe laying work at NH 208 Kerlapuram to Karikkode work in progress. | Kollam WS Sn 3 - AE | |
13 Jul 2023 | DI and hdpe pipe laying work in progress. | Kollam WS Sn 3 - AE | |
10 Jul 2023 | pipe laying work in progress. | Kollam WS Sn 3 - AE | |
06 Jul 2023 | pipe laying work in progress. | Kollam WS Sn 3 - AE | |
04 Jul 2023 | work temporarily stopped due to heavy rain. | Kollam WS Sn 3 - AE | |
01 Jul 2023 | 400mm DI pipe laying work in progress. | Kollam WS Sn 3 - AE | |