Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jun 2024 | 3LL OHSR at Mampuzha - Floor Slab of tank ,Walkway concrete work completed | Kollam PH Dn EE | |
22 Jun 2024 | 3LL OHSR at Mampuzha - Floor Slab of tank ,Walkway concrete work completed. | Kollam WS Sn 3 - AE | |
19 Jun 2024 | 3LL OHSR at Mampuzha - Floor Slab of tank ,Walkway concrete work completed. | Kollam WS Sn 3 - AE | |
18 Jun 2024 | 3LL OHSR at Mampuzha - Floor Slab Shuttering work in progress | Kollam WS Sn 3 - AE | |
14 Jun 2024 | Set out of 8.5LL OHSR at Mekkone started. | Kollam WS Sn 3 - AE | |
13 Jun 2024 | 3LL OHSR at Mampuzha - Floor Slab reinforcement work in progress | Kollam WS Sn 3 - AE | |
10 Jun 2024 | 3LL OHSR at Mampuzha - Floor Slab reinforcement work in progress | Kollam WS Sn 3 - AE | |
07 Jun 2024 | 3LL OHSR at Mampuzha - Floor Slab reinforcement work in progress | Kollam WS Sn 3 - AE | |
03 Jun 2024 | 3LL OHSR at Mampuzha - Floor Slab reinforcement work in progress | Kollam WS Sn 3 - AE | |
29 May 2024 | 3LL OHSR at Mampuzha - Floor Slab reinforcement work in progress | Kollam WS Sn 3 - AE |