Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 May 2023 | 125mm HDPE pipe laying work at karikodu to keralapuram (NHAI) work in progress & 110mm HDPE pipe laying work at Ward 16 panchayath road in progress. | Kollam WS Sn 3 - AE | |
10 May 2023 | 125mm HDPE pipe laying work at karikodu to keralapuram (NHAI) work in progress & 125mm pipe laying work at panchayath road in progress. | Kollam WS Sn 3 - AE | |
09 May 2023 | 125mm HDPE pipe laying work at Karikkodu to Keralapuram (NHAI ) work in progress. | Kollam WS Sn 3 - AE | |
04 May 2023 | 110,125mm HDPE pipe laying work in progress | Kollam WS Sn 3 - AE | |
29 Apr 2023 | 110mm,125mm HDPE pipe laying work and pressure test work in progress. First stage column concreting work completed. | Kollam WS Sn 3 - AE | |
27 Apr 2023 | 110mm,125mm HDPE pipe laying work in progress, Plinth beam work in 3LL OHSR completed. | Kollam PH Dn EE | |
20 Apr 2023 | 110mm,125mm HDPE pipe laying work in progress, Plinth beam work in 3LL OHSR completed. | Kollam WS Sn 3 - AE | |
11 Apr 2023 | 110,125mm HDPE Pipe laying work in progress,3LL OHSR plinth beam pcc completed. | Kollam WS Sn 3 - AE | |
04 Apr 2023 | 110,125mm HDPE laying work in progress | Kollam WS Sn 3 - AE | |
30 Mar 2023 | 110,125mm HDPE pipe laying work in progress. | Kollam PH Dn EE |