| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Oct 2024 | Pipe laying work is in progress. 350mm DI pipe :- 944.79 m, 200mm DI pipe :- 1348.37 m and 160mm PVC pipe:- 4600.79 m laid. | Changanaserry PH Sn - AE | |
| 18 Sep 2024 | Pipe laying work is in progress. 350mm DI pipe :- 944.79 m, 200mm DI pipe :- 1163.37 m and 160mm PVC pipe:- 3909.79 m laid. | Changanaserry PH Sn - AE | |
| 27 Aug 2024 | Pipe laying work is in progress. 350mm DI pipe :- 944.79 m, 200mm DI pipe :- 925.5 m and 160mm PVC pipe:- 3663.79 m laid. | Changanaserry PH Sn - AE | |
| 27 Aug 2024 | Pipe line work completed, Bill under preparation. | Changanaserry PH Sn - AE | |
| 24 Aug 2024 | Pipe laying work is in progress. 350mm DI pipe :- 944.79 m, 200mm DI pipe :- 925.5 m and 160mm PVC pipe:- 3663.79 m laid. | Changanaserry PH Sn - AE | |
| 26 Mar 2024 | Pipe laying work is in progress .586 m pipe laying completed. | Changanaserry PH Sn - AE |