Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Dec 2025 Pipe laying work is in progress. 350 mm DI pipe :- 1375 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11545.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 2829.3 m. Changanaserry PH Sn - AE
11 Nov 2025 Pipe laying work is in progress. 350 mm DI pipe :-1275 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 9501.5 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 2829.3 m Changanaserry PH Sn - AE
22 Oct 2025 Pipe laying work is in progress. 350 mm DI pipe :- 975.1 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 9501.5 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 2829.3 m Changanaserry PH Sn - AE
03 Oct 2025 Pipe laying work is in progress. 350 mm DI pipe :- 975.1 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 9501.5 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 2829.3 m Changanaserry PH Sn - AE
20 Sep 2025 Pipe laying work is in progress. 350 mm DI pipe :- 975.1 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:9501.5 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 2829.3 m Changanaserry PH Sn - AE
09 Sep 2025 Pipe laying work is in progress. 350 mm DI pipe :- 956 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:9300 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 2542 m Changanaserry PH Sn - AE
02 Sep 2025 Pipe laying work is0 in progress. 350 mm DI pipe :- 956 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:9300 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 2542 m Changanaserry PH Sn - AE
02 Sep 2025 Pipe laying work is0 in progress. 350 mm DI pipe :- 956 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:9300 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 2542 m Changanaserry PH Sn - AE
11 Apr 2025 Pipe laying work is in progress. 350 mm DI pipe :- 956 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:-6890 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2000 m, 3. Concrete Road Restoration - 670 m, 4. Tar road restoration- 2392m Changanaserry PH Sn - AE
07 Apr 2025 Pipe laying work is in progress. 350 mm DI pipe :- 956 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:-6890 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 1545 m, 3. Concrete Road Restoration - 390 m, 4. Tar road restoration- 2392m Changanaserry PH Sn - AE