Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Feb 2026 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- Changanaserry PH Sn - AE
19 Feb 2026 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- Changanaserry PH Sn - AE
13 Feb 2026 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- Changanaserry PH Sn - AE
04 Feb 2026 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- Changanaserry PH Sn - AE
29 Jan 2026 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. Changanaserry PH Sn - AE
24 Jan 2026 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. Changanaserry PH Sn - AE
16 Jan 2026 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. Changanaserry PH Sn - AE
09 Jan 2026 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. Changanaserry PH Sn - AE
29 Dec 2025 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. Changanaserry PH Sn - AE
23 Dec 2025 Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. Changanaserry PH Sn - AE