| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Apr 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 17 Apr 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 13 Apr 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 07 Apr 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 31 Mar 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 24 Mar 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 19 Mar 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 13 Mar 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 09 Mar 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 02 Mar 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE |