| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Aug 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m | Changanaserry PH Sn - AE | |
| 31 Aug 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 2430 m, 200 mm DI pipe :- 1412.5 m and 160 mm PVC pipe: 14370 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m | Changanaserry PH Sn - AE | |
| 09 Jul 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m | Changanaserry PH Sn - AE | |
| 22 Jun 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m | Changanaserry PH Sn - AE | |
| 15 Jun 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m | Changanaserry PH Sn - AE | |
| 08 Jun 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 26 May 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 12 May 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 05 May 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE | |
| 29 Apr 2026 | Pipe laying work is in progress. 350 mm DI pipe :- 1400 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe: 11645.50 m laid. Road restoration work ongoing. 1. Construction of the road base by providing GSB - 4942m, 2. Laying old cement concrete interlocking paver blocks - 2100 m, 3. Concrete Road Restoration - 920 m, 4. Tar road restoration- 3649.3 m. | Changanaserry PH Sn - AE |