| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Feb 2025 | Pipe laying work is in progress. 350 mm DI pipe :- 944.79 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:- 6387.79 m laid. Road restoration work ongoing. 1. Construction of the road base by providing Quarry Muck / GSB / WMM - 4417m 2. Laying old cement concrete interlocking paver blocks - 1169 m 3. Concrete Road Restoration - 320.50 m | Changanaserry PH Sn - AE | |
| 26 Jan 2025 | Pipe laying work is in progress. 350 mm DI pipe :- 944.79 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:- 6387.79 m laid. Road restoration work ongoing. 1. Construction of the road base by providing Quarry Muck / GSB / WMM - 4417m 2. Laying old cement concrete interlocking paver blocks - 867 m 3. Concrete Road Restoration - 320.50 m | Changanaserry PH Sn - AE | |
| 16 Jan 2025 | Pipe laying work is in progress. 350 mm DI pipe :- 944.79 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:- 6387.79 m laid. Road restoration work ongoing, Construction of the road base by providing Quarry Muck / GSB / WMM - 4038 m Laying old cement concrete interlocking paver blocks - 803 m Concrete Road Restoration - 99.50 m | Changanaserry PH Sn - AE | |
| 12 Jan 2025 | Pipe laying work is in progress. 350 mm DI pipe :- 944.79 m, 200 mm DI pipe :- 1455.87 m and 160 mm PVC pipe:- 6387.79 m laid. Road restoration work ongoing, Construction of the road base by providing Quarry Muck / GSB / WMM - 3300 m Laying old cement concrete interlocking paver blocks - 790 m Concrete Road Restoration - 99.50 m | Changanaserry PH Sn - AE | |
| 03 Jan 2025 | 1. Construction of the road base by providing Quarry Muck / GSB / WMM - 2626 m 2. Laying old cement concrete interlocking paver blocks - 659 m 3. Concrete Road Restoration - 99.50 m | Changanaserry PH Sn - AE | |
| 13 Nov 2024 | Pipe laying work is in progress. 350mm DI pipe :- 944.79 m, 200mm DI pipe :- 1455.87 m and 160mm PVC pipe:- 6387.79 m laid. Road restoration work ongoing. | Changanaserry PH Sn - AE | |
| 28 Oct 2024 | Pipe laying work is in progress. 350mm DI pipe :- 944.79 m, 200mm DI pipe :- 1400.87 m and 160mm PVC pipe:- 5300.79 m laid. Bill submitted field updation- 45329406/ | Changanaserry PH Sn - AE | |
| 19 Oct 2024 | Pipe laying work is in progress. 350mm DI pipe :- 944.79 m, 200mm DI pipe :- 1348.37 m and 160mm PVC pipe:- 5100.79 m laid. Bill submitted field updation- 45329406/ | Changanaserry PH Sn - AE | |
| 10 Oct 2024 | Pipe laying work is in progress. 350mm DI pipe :- 944.79 m, 200mm DI pipe :- 1348.37 m and 160mm PVC pipe:- 4700.79 m laid. Bill submitted field updation- 45329406/- | Changanaserry PH Sn - AE | |
| 02 Oct 2024 | Pipe laying work is in progress. 350mm DI pipe :- 944.79 m, 200mm DI pipe :- 1348.37 m and 160mm PVC pipe:- 4600.79 m laid. Bill submitted field updation- 45329406/- | Changanaserry PH Sn - AE |