Status Date Overall Project Status Project Officer Contact
27 Apr 2022 Physical Completion - 93% Financial Completion - 80%, Demand for Power Extension-HT connection received from KSEBL. Doors and Window Glass Panel installation in progress. RWPH - Installation of Vertical Transmission Raw Water Pump set in progress. - Electrical cabling work in progress. - Earth leveling in RWPH surroundings. RWPM - Road restoration work pending in municipality road in progress with the supervision of Attingal Municipality authorities. CWPM - Installation of vertical pipeline of 500 mm DI k9 pipe completed Thiruvananthapuram Project AE5
18 Apr 2022 Physical Completion - 92% Financial Completion - 80% (4th and Part Bill Fund Passed by KIIFB) WTP - Floor Plastering work in Clear Water Pump Room - Electrical Cable work in in-commer side of LT Panel - Doors and Window Panel installation - Ground leveling work and removal of debris from site. RWPH - Installation of Vertical Transmission Raw Water Pump set in progress. - Electrical cabling work in progress. - Earth leveling in RWPH surroundings. RWPM - Road restoration work in PWD road at Tachoorkunnu Junction by concreting under the supervision of PWD CWPM - Installation of vertical pipeline of 500 mm DI k9 pipe completed. Thiruvananthapuram Project AE5
12 Apr 2022 Physical Completion - 92% Financial Completion - 80% (4th and Part Bill Fund Passed by KIIFB) WTP - Floor Plastering work in Clear Water Pump Room - Electrical Cable work in in-commer side of LT Panel - Doors and Window Panel installation - Ground leveling work and removal of debris from site. RWPH - Installation of Vertical Transmission Raw Water Pump set in progress. - Electrical cabling work in progress. - Earth leveling in RWPH surroundings. RWPM - Road restoration work in PWD road at Tachoorkunnu Junction by concreting under the supervision of PWD CWPM - Installation of vertical pipeline of 500 mm DI k9 pipe completed. Thiruvananthapuram Project AE5
07 Apr 2022 Clear water Pumping line pipe laying work in progress. Ground leveling work in both WTP and RWPH in progress. Base concreting at entry gate of WTP completed. All layer filter media including fine sand laying completed. Visited DCE (Transmission), KSEB office and requested for earliest provision of demand or estimate for HT connection in both WTP and RWPH. Road restoration work on 140 mtr PWD road started. Plumbing works in Toilet in RWPH in progress. Installation of RWP in progress. Thiruvananthapuram Project AE5
30 Mar 2022 Panchayath road pending restoration work by concreting in progress. External landscaping work, earth leveling work in progress. Electrical cable work in progress in both WTP & RWPH Thiruvananthapuram Project AE5
28 Mar 2022 Recycling tank side wall casting in progress. Drain channel clearance work in progress. Electrical work in progress. Clear water pipe laying work in progress. Site leveling work in progress Thiruvananthapuram Project AE5
18 Mar 2022 4th and part bill proceedings issued from circle office, Trivandrum. Water Treatment Plant (WTP): 1. Floor tiling work completed 2. Electrical wiring work in progress 3. Doors and Windows Frame installation in progress 4. Filter media - Top layer laying in progress 5. Compound wall and Entry gate finishing work in progress. 6. SS Hand Rail work in progress Raw Water Pumping Main (RWPM): 1. Testing of complete 500mm DI K9 pipe completed. Clear Water Pumping main (CLPM): 1. Flanged Pipe - Pipe laying of 300 mtr work in progress. Raw Water Pump House (RWPH): 1. Compound wall and Entry Gate finishing work in progress. 2. Exterior painting work in Transformer room and RWPH completed. 3. RW Pump installation in progress. 4. SS Hand rail work in progress Thiruvananthapuram Project AE5
14 Mar 2022 Water Treatment Plant (WTP): 1. Floor tiling work completed 2. Electrical wiring work in progress 3. Doors and Windows Frame installation in progress 4. Filter media - Top layer laying in progress 5. Compound wall and Entry gate finishing work in progress. 6. SS Hand Rail work in progress Raw Water Pumping Main (RWPM): 1. Testing of complete 500mm DI K9 pipe completed. Clear Water Pumping main (CLPM): 1. Flanged Pipe - Flange welding on pipe in progress. Raw Water Pump House (RWPH): 1. Compound wall and Entry Gate finishing work in progress. 2. Exterior painting work in Transformer room and RWPH completed. 3. RW Pump installation in progress. 4. SS Hand rail work in progress. Thiruvananthapuram Project AE5
07 Mar 2022 RWPM pending 140m of 2200mtr work completed and testing scheduled on 07.03.22.Final layer of filter media laying in all 6 filter beds to be started. Electrical work, wiring and conduit fixing in WTP in progress. Pumps and transformer positioned in WTP , electrical connection works are yet to start. At raw water pump house ,pump and transformer delivered , connection works to be started. White cementing and finishing work of RWPH Transformer room in progress. Entry gate fixing and completion of compound wall both in WTP and RWPH in progress Thiruvananthapuram Project AE5
06 Mar 2022 RWPM pending 140m of 2200mtr work completed and testing scheduled on 07.03.22.Final layer of filter media laying in all 6 filter beds to be started. Electrical work, wiring and conduit fixing in WTP in progress. Pumps and transformer positioned in WTP , electrical connection works are yet to start. At raw water pump house ,pump and transformer delivered , connection works to be started. White cementing and finishing work of RWPH Transformer room in progress. Entry gate fixing and completion of compound wall both in WTP and RWPH in progress. Thiruvananthapuram Proj Dn AEE 2