09 Dec 2021 KIIFB Audit team visited the site and checked documents. Casting of Recycling Water inlet channel, parapet column casting in chemical store room. Plastering of Filter bed inlet channel. Pile work for foundation of Raw Water Pump House foundation completed. Floor finishing work in filter beds. Casting of bottom slab of channel to flash mixer. Plastering of Ceiling for Chemical Room. 2nd lift Column casting in Well cum Pump House. Excavation and Steel + shuttering work for column casting in compound wall. Block work above lintel. Thiruvananthapuram Project AE5
02 Dec 2021 Plastering of Well and Column Steel Work cum Pump House at Kapadakaduavu. Plastering of Filter beds in WTP in progress. Chipping of loose concrete and plastering of recycling tank. Plastering of Raw Water Channel. Compacting of soil at land for transformer at raw water pump house. Piling for Transformer room in raw water pump house to start. Pump for blower installed. Thiruvananthapuram Project AE5
27 Nov 2021 Testing of Raw Water and Clear water Pumps at Factory completed successfully. Testing of 400 KVA and 250 KVA Transformer completed successfully. Casting of Clear Water Channel inside Valve Control Room in Filter House completed. Plastering work in inside of Filter house with white cementing in progress. Piping work for compressed air in filter bed in progress. Block work in Well cum Pump House of Raw Water well at Kapadakadavu in progress. Thiruvananthapuram Project AE5
20 Nov 2021 Recycling Tank Plastering work. Wall plastering work in WTP, Transformer room lintel and slab casting. Raw Water Channel to Filter house and Clear water channel plastering work in progress. Various pipeline work inside WTP for aerator, clear water transfer etc. in progress. Gap filling of cut for pipeline from Wash Water Tank completed. Applying of white cement in inside walls of Filter House. Well cum Pump House at Kapdakadavu, lintel casting completed Thiruvananthapuram Project AE5
15 Nov 2021 Casting of Floor Slab in Well Cum Pump House completed. Joint Inspection with KSEB AE of Avanavanchery and team conducted both at well site and WTP site for finalizing the extension of power lines for the project. Exterior & Interior plastering work for Filter House in progress. GI Pipe work and PVC piping for blower in filter bed in progress. Transformer house at WTP block work completed. Casting of sunshade slab completed. White cement painting inside filter house wall in progress. Thiruvananthapuram Project AE5
06 Nov 2021 Steel work for Floor Slab in Well Cum Pump House in Progress. Exterior & Interior plastering work for Filter House in progress. GI Pipe work and PVC piping for blower in filter bed in progress. Valve installation for drain of clarifocculator completed. Transformer house at WTP block work completed. Shuttering for sunshade work in progress. White cement painting inside filter house wall in progress. Thiruvananthapuram Project AE5
25 Oct 2021 Pipe work inside filter house in progress. QAP of 400 KVA Transformer for raw water pump house vetted and approved by Specialist Officer (Electrical). Floor Slab beam work in Well Cum Pump House work in progress. Clear Water Channel plastering work inside filter house in progress Thiruvananthapuram Project AE5
16 Oct 2021 Wash water tank top slab casting completed. Raw Water Well cum Pump House final lift casting completed. Transformer House at WTP plinth beam casting completed. Filter House Parapet work completed. Pipe work inside filter house in progress. Welcome tank work in progress. QAP of pumps for vetted and approved by Specialist Officer (Electrical) Thiruvananthapuram Project AE5
11 Oct 2021 3rd and part bill prepared. Pressure testing of DI pipe laid from polytechnic to WTP completed. Filter House Parapet wall brick work in progress. Pipe work inside filter house in progress. Raw water well one more upper lift casting completed. Total 17.0m casting from top completed. Welcome tank work in progress. 02. QAP of pumps for vetting submitted before Specialist Officer (Electrical). Thiruvananthapuram Project AE5
02 Oct 2021 Pressure testing of DI pipe laid from polytechnic to WTP failed and asked for redo. Filter House Parapet wall brick work in progress. Pipe work inside filter house in progress. 03 nos. of footing casted for Transformer house. Total 06 nos. f foting completed. Raw water well one more upper lift casting completed. Welcome tank work in progress. 02 nos. of Valves inside well fixed. QAP withdrawer from CET due to slow progress of action. Thiruvananthapuram Project AE5