Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Dec 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. Thiruvananthapuram Project AE5
30 Nov 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. Thiruvananthapuram Project AE5
28 Nov 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH Thiruvananthapuram Project AE5
26 Nov 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH Thiruvananthapuram Project AE5
25 Nov 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. Thiruvananthapuram Project AE5
24 Nov 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. Thiruvananthapuram Project AE5
22 Nov 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. Thiruvananthapuram Project AE5
21 Nov 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. Thiruvananthapuram Project AE5
19 Nov 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. Thiruvananthapuram Project AE5
18 Nov 2022 Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. Thiruvananthapuram Project AE5