Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Mar 2022 RWPM pending 140m of 2200mtr work in progress. Filter media filling in all 6 filter house in progress. Electrical work, wiring and condut fixing in WTP in progress. White cementing and finishing work of RWPH Transformer room in progress. Entry gate fixing and completion of compound wall both in WTP and RWPH in progress. Thiruvananthapuram Project AE5
23 Feb 2022 Raw Water Pumping main Road Crossing work 90% work completed. Laying of first layer of filter media in filter bed completed. Painting work in metal part and external painting work in parapet wall of WTP in progress. Tiling work in WTP in progress. Electrical work in WTP like cable tray installation in progress. Thiruvananthapuram Project AE5
20 Feb 2022 Laying of filter media in filter bed in progress. Painting work in metal part and external painting work in parapet wall of WTP in progress. Road cutting in PWD road and laying of 500mm DI k9 raw water pumping line in progress. 90 mtr of total 140 mtr remaining completed. Road crossing work in progress. No road cutting work on this Sunday. Tiling work in WTP in progress. Electrical work in WTP like cable tray installation in progress. Thiruvananthapuram Project AE5
14 Feb 2022 Floor Tile work in progress. PWD road cutting work started. Transformer room plastering work in Raw Water Pump House. Sample external painting on WTP for selection of colour done. HT connection request with KSEB still pending for want of completion of dues in existing LT connection. Shutter gate for Transformer room and Clear Water Pump House installed. Pebble washing for filter house in progress. Electrical work in clear water pump house in progress. Thiruvananthapuram Project AE5
08 Feb 2022 Raw Water Pump House Transformer Room plastering works , Raw Water Pumping Main balance laying near to well almost completed. scour line works at well site to be started. Civil works of WTP (finishing works) are in progress. Raw water pumping main road crossing (140ms) works initiated Thiruvananthapuram Proj Dn AEE 2
03 Feb 2022 Raw Water Pump House Plastering work in progress. Raw Water Pump House Transformer Room roof slab concreting completed. intake pipe work completed. Raw Water Pumping Main, 5 nos. of pending 500mm DI pipe laying in Tachoorkunnu -Valiyakunnu completed and testing completed successfully. Plastering work in chemical room, compound wall work, tile works etc in progress in WTPsite. Clear water pump and motor placed. RWPM work near well site around 40 metres started Thiruvananthapuram Proj Dn AEE 2
02 Feb 2022 Raw Water Pump House Plastering work in progress. Raw Water Pump House Transformer Room roof slab concreting completed. intake pipe work completed. Raw Water Pumping Main, 5 nos. of pending 500mm DI pipe laying in Tachoorkunnu -Valiyakunnu completed and testing completed successfully. Plastering work in chemical room, compound wall work, tile works etc in progress in WTPsite. Clear water pump and motor placed. Remaining RWPM near well site around 40 metres will start today Thiruvananthapuram Proj Dn AEE 2
31 Jan 2022 Raw Water Pump House External Plastering work completed. Internal plastering work in progress. Raw Water Pump House Transformer Room, 2nd lift column casting and block work in progress. Extension of flanged intake pipe in river bed in progress. Raw Water Pumping Main, 5 nos. of pending 500mm DI pipe laying in Tachoorkunnu-Valiyakunnu road completed and testing in progress. Plastering work in chemical room, compound wall work, lateral pipe fixing in filter beds in progress at WTP. Slab casting completed in Raw Water Pump House Transformer room. Thiruvananthapuram Project AE5
27 Jan 2022 Raw Water Pump House External Plastering work completed. Internal plastering work in progress. Raw Water Pump House Transformer Room, 2nd lift column casting and block work completed. Roof slab shuttering work in progress. Extension of flanged intake pipe in river bed in progress. Raw Water Pumping Main, 5 nos. of pending 500mm DI pipe laying in Tachoorkunnu-Valiyakunnu road finished and Pressure Testing procedure started. Plastering work in chemical room, compound wall work, lateral pipe fixing in filter beds finished at WTP. Floor tiles work at WTP started Thiruvananthapuram Proj Dn AEE 2
21 Jan 2022 Raw Water Pump House External Plastering work completed. Internal plastering work in progress. Raw Water Pump House Transformer Room, 2nd lift column casting and block work in progress. Extension of flanged intake pipe in river bed in progress. Raw Water Pumping Main, 5 nos. of pending 500mm DI pipe laying in Tachoorkunnu-Valiyakunnu road in progress. Plastering work in chemical room, compound wall work, lateral pipe fixing in filter beds in progress at WTP. Thiruvananthapuram Project AE5