Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Sep 2021 Raw Water Pumping Pipe line laid inside Attingal Polytechnic conducted and leakage found. Asked for retesting. Filter House Over Head Wash Water Tank side wall 2nd lift casting completed. Blowers installed at filter house. Pipe work inside filter house in progress. Land filling for Transformer house in progress. 2nd Clarifoculator finishing work in progress. Thiruvananthapuram Project AE5
24 Sep 2021 Raw Water Pumping Pipe line laid inside Attingal Polytechnic conducted and leakage found. Asked for retesting. Filter House Over Head Wash Water Tank side wall 2nd lift shuttering work completed. Blowers installed at filter house. Pipe work inside filter house in progress. Land filling for Transformer house in progress. 2nd Clarifoculator finishing work in progress. Thiruvananthapuram Project AE5
22 Sep 2021 Raw Water Pumping Pipe line from polytechnic to WTP pressure re-testing in progress. Filter House Over Head Tank side wall final casting completed. Thiruvananthapuram Project AE5
14 Sep 2021 Raw water Well at Ayilamkadavu Bottom Plugging - Side wall 1st lift casting completed. Raw Water Pumping Pipe line from polytechnic to WTP pressure re-testing in progress. Filter House Over Head Tank side wall first lift steel work completed, shuttering work in progress. Thiruvananthapuram Project AE5
08 Sep 2021 Raw water Well at Ayilamkadavu Bottom Plugging Steel work completed. Well welcome chamber casting started. Raw water channel to clarifocculator casting in progress. Raw Water Pumping Pipe line from polytechnic to WTP pressure re-testing in progress. Filter House Over Head Tank Steel work and shuttering in progress. Recycling Tank Final lift completed. Thiruvananthapuram Project AE5
05 Sep 2021 Filter House Slab Casting completed. Recycling Tank wall 2nd lift casting completed. Raw water intake well bottom PCC completed. Bottom Plugging RCC work started. Thiruvananthapuram Project AE5
02 Sep 2021 Recycling Tank Side wall First lift casting completed. 2nd lift shuttering work in progress. Top Slab of Filter House Steel work in progress. Intake Well River depth measurements at various locations completed. Intake well bottom casting drawing finalized. Thiruvananthapuram Project AE5
31 Aug 2021 Recycling Tank Side wall First lift casting in progress. Top Slab of Filter House Steel work in progress. Intake Well River depth measurements at various locations completed. Thiruvananthapuram Project AE5
28 Aug 2021 Recycling tank Bottom RCC completed. Deshuttering Done. Shuttering work for first lift wall of recycling tank in progress. 28 day Cube Testing of sunshade slab of filter house conducted successfully. Thiruvananthapuram Project AE5
24 Aug 2021 The shuttering & steel works in progress for the roof slab of the filter house in the filter box(except the porch portion). Mechanical erection works inside the Clarifloculattor-2 in progress ; Well excavation works in progress & difficult due to the presence of rock in the well(now excavation done for a depth approximately 16m) ,Recycling tank excavation completed ,Anchor block(1no) in front of Clarifier completed Thiruvananthapuram Project AE5