Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Jan 2022 Road Restoration work started in Municipality Roads. External Plastering work in Raw Water Pump House in progress. Block work for Transformer Room. White cementing of exterior walls of WTP in progress. Tile work for Filter beds. Painting work of steel structures in progress. Chlorinator room plastering work in progress Thiruvananthapuram Project AE5
12 Jan 2022 Legislative Assembly Committee visited work site which included, Shri. E Chandrashekaran (MLA Kanjangadu), Shri. Kadakampally Surendran (MLA Kazhakoottam), Shri. D.K. Murali (MLA Vamanapuram). Road Restoration work started in Municipality Roads. External Plastering work in Raw Water Pump House in progress. Block work for Transformer Room. White cementing of exterior walls of WTP in progress. Tile work for Filter beds. Painting work of steel structures in progress. Chlorinator room plastering work in progress Thiruvananthapuram Project AE5
08 Jan 2022 Column casting in Raw Water Transformer room completed. Tiling work in filter beds in progress. Outer ring of aerator casting in progress. Compound wall construction for WTP in progress. Roof plastering of chemical room in progress. Thiruvananthapuram Project AE5
07 Jan 2022 Column casting in Raw Water Transformer room completed. Tiling work in filter beds in progress. Outer ring of aerator casting in progress. Compound wall construction for WTP in progress. Roof plastering of chemical room in progress Thiruvananthapuram Project AE5
31 Dec 2021 Parapet wall of well cum pump house. Plinth beam work for raw water pump house transformer room completed. Plastering work and final alignment work of welcome chember for well cum pump house in progress. Painting work on exterior metal parts, tiling work in filter beds, plastering work in terrace slab of chemical room in progress Thiruvananthapuram Project AE5
30 Dec 2021 Painting Painting work in steel frames of Clarifocculator and other finishing work in progress. All pumps and accessories received at site on 20.12.2021 Thiruvananthapuram Project AE5
20 Dec 2021 Bank Guarantee in the name of EE, Roads Division, PWD, submitted to PWD. Bar Bending work for slab and beam casting of well cum pump house. Sinking of welcome chamber for raw water in progress. Thiruvananthapuram Project AE5
19 Dec 2021 Plastering of Clarifocculator bottom. Plastering in Chemical storage room. Shuttering work for beam casting in well cum pump house. Sinking of welcome chambers for pump house. Thiruvananthapuram Project AE5
13 Dec 2021 At well site , corbel concreting completed. At WTP site plastering work of Transformer room, Filter room gullet in progress. Plastering of filters completed Thiruvananthapuram Project AE5
13 Dec 2021 At well site , corbel concreting completed. At WTP site plastering work of Transformer room, Filter room gullet in progress. Plastering of filters completed Thiruvananthapuram Proj Dn AEE 2