Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Nov 2022 |
Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. |
Thiruvananthapuram Project AE5 |
|
16 Nov 2022 |
Trail Run Conducted. Snag list provided to contractor for commissioning of WTP & RWPH. |
Thiruvananthapuram Project AE5 |
|
09 Nov 2022 |
Review meeting on completion of work conducted at the office room of MLA. WTP trail running with water taken upto filter bed. Inlet water testing completed. Filter bed washing in progress. Clarifocculator working satisfactorily. Testing of electrical equipments including back wash motor in progress. |
Thiruvananthapuram Project AE5 |
|
19 Oct 2022 |
Payment made for following charges as security deposit as per KSEB demand for availing HT connection. WTP - Rs. 5,12,808.00 RWPH - Rs. 7,73,693.00. Agreement signed with DCE KSEB and Electrical connection awaited |
Thiruvananthapuram Project AE5 |
|
15 Oct 2022 |
Payment made for following charges as security deposit as per KSEB demand for availing HT connection. WTP - Rs. 5,12,808.00 RWPH - Rs. 7,73,693.00. Agreement signed with DCE KSEB and Electrical connection awaited. |
Thiruvananthapuram Project AE5 |
|
10 Oct 2022 |
KSEB Demand for HT connection received. Payment of following charges as security deposit for availing HT connection. WTP - Rs. 5,12,808.00 RWPH - Rs. 7,73,693.00. Fund Sanctioned by KIIFB. |
Thiruvananthapuram Project AE5 |
|
27 Sep 2022 |
KSEB Demand for HT connection received. Payment of following charges as security deposit for availing HT connection. WTP - Rs. 5,12,808.00 RWPH - Rs. 7,73,693.00. Bill uploaded in KIIFB and sanction of fund awaited. |
Thiruvananthapuram Project AE5 |
|
13 Sep 2022 |
KSEB Demand for HT connection received. Payment of following charges as security deposit for availing HT connection. WTP - Rs. 5,12,808.00 RWPH - Rs. 7,73,693.00 |
Thiruvananthapuram Proj Dn AEE 2 |
|
31 Aug 2022 |
KSEB Demand for HT connection received. Payment of following charges as security deposit for availing HT connection.
WTP - Rs. 5,12,808.00
RWPH - Rs. 7,73,693.00 |
Thiruvananthapuram Project AE5 |
|
24 Aug 2022 |
No major work at site. Work on hold for want of Electrical HT connection. KSEBL infrastructure work completed. Electrical Inspectorate inspection completed on 07.07.2022 and NoC Received. Application submitted in KSEBL for HT Connection. Awaiting demand letter from KSEBL. File pending with AXE, KSEB Attingal from 09.08.2022. Joint visit completed on 17.08.2022. File yet to reach KSEB Circle Office. |
Thiruvananthapuram Project AE5 |
|