Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress..., Centrifuge building plinth beam reinforcement work in progress Kollam Project HD
08 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress. Kollam Project HD
07 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber form work in progress..,Centrifuge building plinth beam Reinforcement work in progress.., Kollam Project HD
06 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber form work in progress..,Centrifuge building plinth beam steel making work in progress..,Pre-Treatment unit Grit chamber form work & beam reinforcement work in progress Kollam Project HD
05 Jan 2023 8 components completed - 100% out of 34 components ( 3 components -above 90 % completed , 8 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber form work in progress..,Centrifuge building plinth beam steel making work in progress..,Pre-Treatment unit Grit chamber form work & beam reinforcement work in progress. Kollam Project Dn EE
04 Jan 2023 8 components completed - 100% out of 34 components ( 3 components -above 90 % completed , 8 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber form work in progress..,Centrifuge building plinth beam steel making work in progress..,Dilution pump (2 nos),Clarifier mechanism,Sludge thickner mechanism received. Kollam Project HD
03 Jan 2023 8 components completed - 100% out of 34 components ( 3 components -above 90 % completed , 8 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 4 supplied at site..,- Mbbr 1 & 2 civil work completed Kollam Project HD
02 Jan 2023 7 components completed - 100% out of 34 components ( 3 components -above 90 % completed , 8 components - above 80 % completed ) ... for electro mechanical items - 20 factory inspection completed out of 32 items and 4 supplied at site..,Sludge drying bed wall reinforcement work in progress..,Pre-treatment unit grit chamber form work in progress.Sludge drying bed wall reinforcement work in progress Kollam Project HD
01 Jan 2023 7 components completed - 100% out of 34 components ( 3 components -above 90 % completed , 8 components - above 80 % completed ) ... for electro mechanical items - 20 factory inspection completed out of 32 items and 4 supplied at site..,Sludge drying bed wall reinforcement work in progress..,Pre-treatment unit grit chamber form work in progress. Kollam Project HD
31 Dec 2022 7 components completed - 100% out of 34 components ( 3 components -above 90 % completed , 8 components - above 80 % completed ) ... for electro mechanical items - 20 factory inspection completed out of 32 items and 4 supplied at site..,Sludge drying bed wall reinforcement work in progress..,Pre-treatment unit grit chamber form work in progress.MBBR 2 Walk way & side wall Rcc work Completed..,MBBR 4 final lift Baffle wall Rcc work Completed. Kollam Project HD