Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Nov 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 70394m, 110mm PE-3199m, 140mm-1887m, 160mm - 8276m, 350mm DI -987m, 400mm DI-3061m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 91689m. 4750 HTCs provided, work in progress. Kozhikode Project Dn AE5
20 Oct 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 70394m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-3061m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 91606m. 4490 HTCs provided, work in progress. Kozhikode Project Dn AE5
28 Sep 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 69954m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-2900m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 91005m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5
04 Aug 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 69954m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-2900m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 91005m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5
29 Jul 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 69500m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-2900m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 90551m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5
26 Jul 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 68400m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-2900m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 89451m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5
19 Jul 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 68400m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-2900m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 89451m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5
24 Jun 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 67287m, 110mm PE-3021m, 140mm-1399m, 160mm - 8200m, 350mm DI -1026m, 400mm DI-2180m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 86998m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5
16 Jun 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 67287m, 110mm PE-3021m, 140mm-1399m, 160mm - 8200m, 350mm DI -1026m, 400mm DI-2180m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 86998m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5
27 May 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 67287m, 110mm PE-3021m, 140mm-1399m, 160mm - 8200m, 350mm DI -1026m, 400mm DI-2180m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 86998m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5