Status Date Overall Project Status Project Officer Contact
30 May 2022 Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. LAYING - 90mm PE- 30307m, 110mm PE-2183m laid, Total pipe laid =32490m. Kozhikode Project Dn AE5
20 May 2022 materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. LAYING - 90mm PE- 26150m, 110mm PE-2183m laid, Total pipe laid =28333m. Kozhikode Project Dn AE5
12 May 2022 materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. LAYING - 90mm PE- 19500m, 110mm PE-1200m laid, Total pipe laid =20700m. Kozhikode Project Dn AE5
06 May 2022 Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. LAYING - 90mm PE- 16280m, 110mm PE-700m laid, Total pipe laid =16980 m. Kozhikode Project Dn AE5
28 Apr 2022 materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. LAYING - 90mm PE- 13400m, 110mm PE-500m laid, Total pipe laid =13900 m. Kozhikode Project Dn AE5
22 Apr 2022 Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. 90mm - 8500m, 110mm -400m laid, Total pipe laid =8900 m. Kozhikode Project Dn AE5
13 Apr 2022 materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. 90mm - 4500m, 110mm -300m laid. Kozhikode Project Dn AE5
25 Mar 2022 materials supplied - 1.90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. Kozhikode Project Dn AE5
14 Mar 2022 Supply in progress, 90mm PE -10000m supplied Kozhikode Project Dn AE5
26 Feb 2022 Supply in progress Kozhikode Project Dn AE5