Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2021-2022 Phase II: Providing FHTCs at Chekkiad Grama Panchayath by the Construction of new RCC OH Tank of capacity 12.50 Lakh Litre, Laying new Gravity main and Laying new Distribution line

Project JJM 2021-2022 Phase II: Providing FHTCs at Chekkiad Grama Panchayath by the Construction of new RCC OH Tank of capacity 12.50 Lakh Litre, Laying new Gravity main and Laying new Distribution line
Project Code CLTJJM09218582
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing FHTCs at Chekkiad Grama Panchayath by the Construction of new RCC OH Tank of capacity 12.50 Lakh Litre, Laying new Gravity main and Laying new Distribution line
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
AS Amount (Rs) 315800000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 309400000
TS Number TS/2021-2022/2021/32992
Total Bill Submitted (Rs) 235932801
Total Bill Paid (Rs) 235932801
Population Benefitted 24246
Capacity in MLD 27.00
Actual Project Completion Date Date is not specified
Coverage Chekkiad Grama Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM 2021-2022 Phase II: Providing FHTCs at Chekkiad Grama Panchayath by the Construction of new RCC OH Tank of capacity 12.50 Lakh Litre, Laying new Gravity main and Laying new Distribution line Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Nov 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 70394m, 110mm PE-3199m, 140mm-1887m, 160mm - 8276m, 350mm DI -987m, 400mm DI-3061m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 91689m. 4750 HTCs provided, work in progress. Kozhikode Project Dn AE5
20 Oct 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 70394m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-3061m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 91606m. 4490 HTCs provided, work in progress. Kozhikode Project Dn AE5
28 Sep 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 69954m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-2900m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 91005m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5
04 Aug 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 69954m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-2900m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 91005m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5
29 Jul 2023 OHSR - Roof slab Work completed, Plastering work in progress . Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 69500m, 110mm PE-3199m, 140mm-1880m, 160mm - 8200m, 350mm DI -987m, 400mm DI-2900m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 90551m. 4426 HTCs provided, work in progress. Kozhikode Project Dn AE5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/01/2022
Scheduled date of Completion of the Project 10 Nov 2022
Expected date of Completion 30/06/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 23 Nov 2021

Other details

Project Officers View