Status Date |
Overall Project Status |
Project Officer |
Contact |
10 May 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Roof slab Work completed, Side wall work completed, Roof slab work completed. Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 67000m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1500m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 86002m. 4426 HTCs provided, work in progress. |
Kozhikode Project Dn AE5 |
|
06 May 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Roof slab Work completed, Side wall work completed, Roof slab work completed. Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 66000m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1296m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 84798m. 4426 HTCs provided, work in progress.
|
Kozhikode Project Dn AE5 |
|
27 Apr 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Roof slab Work completed, Side wall work completed, bottom slab work in progress. Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 66000m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1296m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 84798m. 4426 HTCs provided, work in progress.
|
Kozhikode Project Dn AE5 |
|
25 Apr 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Bottom slab Work completed, Side wall work completed, bottom slab work in progress. Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 66000m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1296m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 84798m. 4426 HTCs provided, work in progress.
|
Kozhikode Project Dn AE5 |
|
13 Apr 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Bottom slab Work completed, Side wall 3st lift work completed, 4th lift work in progress. Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 66000m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1296m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 84798m. 4426 HTCs provided, work in progress.
|
Kozhikode Project Dn AE5 |
|
05 Apr 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Bottom slab Work completed, Side wall 3st lift work completed, 4th lift work in progress. Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 65600m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1296m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 84398m. 4426 HTCs provided, work in progress.
|
Kozhikode Project Dn AE5 |
|
25 Mar 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Bottom slab Work completed, Side wall 3st lift work completed, Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 65000m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1296m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 83798m. 4426 HTCs provided, work in progress.
|
Kozhikode Project Dn AE5 |
|
20 Mar 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Bottom slab Work completed, Side wall 2st lift completed, Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 64930m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1296m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 83728m. 4426 HTCs provided, work in progress.
|
Kozhikode Project Dn AE5 |
|
10 Mar 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Bottom slab Work completed, Side wall 2st lift completed, Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 64230m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1296m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 83028m. 4426 HTCs provided, work in progress.
|
Kozhikode Project Dn EE |
|
22 Feb 2023 |
OHSR - Footing and Column upto bottom floor beam completed, Bottom slab Work completed, Compound wall in progress , Materials supplied - 90mm dia PE- 88080m, 110mm dia PE- 4300m, 140mm dia PE - 3120m, 160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6670m, Total =118128.5m. LAYING - 90mm PE- 61531m, 110mm PE-3021m, 140mm-1399m, 160mm - 8171m, 350mm DI -1026m, 400mm DI-1296m, 200mm -2517m, 250mm-1368m laid, Total pipe laid = 80329m. 4426 HTCs provided, work in progress. |
Kozhikode Project Dn AE5 |
|