Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Oct 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 50180m, 110mm PE-2590m, 140mm-1399m, 160mm - 5050m, 350mm DI -1026m, 400mm DI-1296m, 200mm -1652m, 250mm-356m laid, Total pipe laid = 63549m. 3911 HTCs provided. |
Kozhikode Project Dn AE5 |
|
19 Oct 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 50180m, 110mm PE-2590m, 140mm-1399m, 160mm - 4200m, 350mm DI -1026m, 400mm DI-1296m, 200mm -1652m, 250mm-356m laid, Total pipe laid = 62699m. 3911 HTCs provided.
|
Kozhikode Project Dn AE5 |
|
03 Oct 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 49781m, 110mm PE-2590m, 140mm-989m, 160mm - 4088m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid = 61636m. 3911 HTCs provided. |
Kozhikode Project Dn AE5 |
|
30 Sep 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 49680m, 110mm PE-2590m, 140mm-989m, 160mm - 4088m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid = 61535m. 3911 HTCs provided. |
Kozhikode Project Dn AE5 |
|
27 Sep 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 49100m, 110mm PE-2590m, 140mm-989m, 160mm - 4088m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid = 60955m. 3911 HTCs provided. |
Kozhikode Project Dn AE5 |
|
19 Sep 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 47750m, 110mm PE-2590m, 140mm-989m, 160mm - 4088m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =59605m. 3911 HTCs provided.
|
Kozhikode Project Dn AE5 |
|
06 Sep 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 44631m, 110mm PE-2590m, 140mm-989m, 160mm - 3768m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =56166m. 3906 HTCs provided.
|
Kozhikode Project Dn AE5 |
|
30 Aug 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 44631m, 110mm PE-2590m, 140mm-989m, 160mm - 3768m, 350mm DI - 921m, 400mm DI-1296m, 200mm -1652m, 250mm-356m laid, Total pipe laid =56203m. 3900 HTCs provided.
|
Kozhikode Project Dn AE4 |
|
25 Aug 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 44631m, 110mm PE-2590m, 140mm-989m, 160mm - 3768m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =56166m. 3900 HTCs provided. |
Kozhikode Project Dn AE5 |
|
23 Aug 2022 |
OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 44631m, 110mm PE-2590m, 140mm-989m, 160mm - 3556m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =55954m. 2600 HTCs provided. |
Kozhikode Project Dn AE5 |
|