Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Aug 2022 OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 43330m, 110mm PE-2590m, 140mm-989m, 160mm - 3556m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =54653m. Kozhikode Project Dn AE5
11 Aug 2022 OHSR - Footing and column up to plinth beam nearing completion, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 43184m, 110mm PE-2575m, 140mm-125m, 160mm - 3556m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =53628m. Kozhikode Project Dn EE
04 Aug 2022 OHSR - Footing and column up to plinth beam in progress, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 43184m, 110mm PE-2575m, 140mm-125m, 160mm - 3556m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =53628m. Kozhikode Project Dn AE5
20 Jul 2022 OHSR - Footing and column up to plinth beam in progress, Compound wall in progress , Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 43184m, 110mm PE-2575m, 140mm-125m, 160mm - 3556m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =53628m. Kozhikode Project Dn AE5
15 Jul 2022 OHSR - Footing work in progress, Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 43184m, 110mm PE-2575m, 140mm-125m, 160mm - 3556m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =53628m. Kozhikode Project Dn AE5
30 Jun 2022 OHSR - Footing work in progress, Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 39995m, 110mm PE-2575m, 140mm-125m, 160mm - 3556m, 350mm DI - 921m, 400mm DI-1259m, 200mm -1652m, 250mm-356m laid, Total pipe laid =50439m. Kozhikode Project Dn AE5
24 Jun 2022 OHSR - Footing work in progress, Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 37450m, 110mm PE-2575m, 160mm - 3416m, 350mm DI - 831m, 400mm DI-1136m, 200mm -980m, 250mm-356m laid, Total pipe laid =46744m. Kozhikode Project Dn AE5
20 Jun 2022 OHSR - Footing work in progress, Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m,200DI -3949m, 250mm DI-2304.5m, 350mm DI-995m,40mm DI-6666m, Total =118124.5m. LAYING - 90mm PE- 36800m, 110mm PE-2575m, 160mm - 2855m, 350mm DI - 545m, 400mm DI-463m, 200mm -250m, 250mm-356m laid, Total pipe laid =43844m. Kozhikode Project Dn AE5
14 Jun 2022 Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. LAYING - 90mm PE- 35179m, 110mm PE-2575m, 160mm - 1806m, 250mm DI - 545m, 350mm DI-180m laid, Total pipe laid =40285m. Kozhikode Project Dn AE5
02 Jun 2022 Materials supplied - 1. 90mm dia PE- 88080m, 2.110mm dia PE- 4300m, 3.140mm dia PE - 3120m, 8.160mm dia PE - 8710m, Total =104210m. LAYING - 90mm PE- 32280m, 110mm PE-2183m, 160mm - 500m laid, Total pipe laid =34963m. Kozhikode Project Dn AE5