Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Feb 2024 |
KIIFB Kondotty-Package 2- Construction of 6LL Capacity OHSR at Chemmalaparamba, 8 LL Capacity OHSR Melengadi, Laying Transmission mains to various reserviours and distribution to zone 4 Melangadi- OHSR work at Chemmelapparaba & Melangadi Structural work completed ,Finishing works progressing . Laying distribution work almost nearing completion. Pending PWD road works started. Road restoration and inter connection works are progressing.
KIIFB Kondotty-Package 2A- Construction of 14LL Capacity OHSR at Kumbalapara, supplying and laying pumping main from WTP to Kumbalapara, laying gravity mains to various reserviours, supply, errection and commiisioning of clear water pump set at WTP site-14.00LL OHSR work completed , Laying 350mm pumping main for 14.60km completed
KIIFB Kondotty - Package I- construction of 19 MLD water treatment palnt- 600 mm DI K9 raw water pumping main - 270 HP VT raw wate pumpset - Work completed-Commissioning work on going
KIIFB Kondotty-Package 3B - Supply and laying distribution system to zone 5A,5B, 6 and 7 and Laying pumping main and gravity mains and distribution system to Cheruppady and Moochikundu zone- Work re tendered
|
Malappuram Project Dn AE6 |
|
25 Oct 2023 |
Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing. Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- work completed package 3 B Work re tendered |
Malappuram Project Dn AE6 |
|
16 Sep 2023 |
Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing. Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- work completed package 3 B Work re tendered |
Malappuram Project Dn AE6 |
|
18 Aug 2023 |
work on going |
Malappuram Project Dn AE6 |
|
07 Aug 2023 |
Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing. Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- work completed package 3 B Work re tendered |
Malappuram Project Dn AE6 |
|
22 Jul 2023 |
Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing. Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- work completed package 3 B Work re tendered |
Malappuram Project Dn AE6 |
|
15 Jun 2023 |
Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing. Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- work completed package 3 B Work re tendered |
Malappuram Project Dn AE6 |
|
24 May 2023 |
Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing. Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- work completed package 3 B Work re tendered |
Malappuram Project Dn AE6 |
|
11 May 2023 |
Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing.
Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month.
Package 3A- work completed
package 3 B Work re tendered |
Malappuram Project Dn AE6 |
|
05 May 2023 |
Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing.Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- The pipe laying work of zone 1 and zone 2 is completed and charged. Pipe laying work of zone almost pipe laying work completed all roads except NH road for 19Km for non-getting permission from NHAI. Now this work is in stand still. Contractor approached high court for decision, package 3 B Work re tendered |
Malappuram Project Dn AE6 |
|