Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Mar 2021 overall 17 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
09 Mar 2021 overall 17 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
07 Mar 2021 overall 17 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
03 Mar 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
01 Mar 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
26 Feb 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig Malappuram Project Dn AE6
25 Feb 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig Malappuram Project Dn AE6
24 Feb 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig Malappuram Project Dn AE6
23 Feb 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig Malappuram Project Dn AE6
20 Feb 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 55 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig Malappuram Project Dn AE6