Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Mar 2021 |
overall 17 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign |
Malappuram Project Dn AE6 |
|
09 Mar 2021 |
overall 17 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign |
Malappuram Project Dn AE6 |
|
07 Mar 2021 |
overall 17 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign |
Malappuram Project Dn AE6 |
|
03 Mar 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign |
Malappuram Project Dn AE6 |
|
01 Mar 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign |
Malappuram Project Dn AE6 |
|
26 Feb 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig |
Malappuram Project Dn AE6 |
|
25 Feb 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig |
Malappuram Project Dn AE6 |
|
24 Feb 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig |
Malappuram Project Dn AE6 |
|
23 Feb 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 58 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig |
Malappuram Project Dn AE6 |
|
20 Feb 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 55 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig |
Malappuram Project Dn AE6 |
|