Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Mar 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall completed and roof slab work in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slab work completed, side wall work completed, roof slab work in progress 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-fully supplied and 5000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c TS is obtained and the work is tendered, overall 58 percentage of work completed Malappuram Project Dn AE6
17 Feb 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed Malappuram Project Dn AE6
11 Feb 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed Malappuram Project Dn AE6
02 Feb 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed Malappuram Project Dn AE6
01 Feb 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed Malappuram Project Dn AE6
27 Jan 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed Malappuram Project Dn AE6
18 Jan 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed Malappuram Project Dn AE6
13 Jan 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed Malappuram Project Dn AE6
12 Jan 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed Malappuram Project Dn AE6
11 Jan 2022 package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed Malappuram Project Dn AE6