Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB Project: Tranche 13: WRD004-02- lmprovements to WSS of Kondotty Municipality- Phase-ll

Project KIIFB Project: Tranche 13: WRD004-02- lmprovements to WSS of Kondotty Municipality- Phase-ll
Project Code MLPKIIFB0619570
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Improvements to water supply to Kondotty Muncipality- phase II. Intake well: Existing 10 meter dia intake well cum pump house at Erattamuzhi. Pumping systems:2 nos of 270 HP VT pump set, raw water pumping main-600mm DI K9-1600 meter Transmission lines:350mm DI K9-16000 meter, , 300 mm DI K9-2770m, 250 mm DI K9-5030m, 200 mm DI K9-4420 m, 150mm DI K9-4580 m, 100 mm DI K9-3620m Water treatment plant: 19 MLD WTP at Rayankode hills OH tanks: 14 LL capacity OHSR at Kumbalapara, 8 LL capacity OHSR at Melangadi, 6 LL capacity OHSR at Chemmalaparamba GL Tanks:- Existing 3LL capacity GLSR at Block office, kondotty, Existing 2 LL capacity GLSR at Kalaoth, Existing 3 LL capacity GLSR at Meleparamba, proposed 0.5 LL capacity GLSR at shamji nagar, 0.3 LL capacity GLSR at Moochikundu and cherupadi Supply lines: 160mm PVC Cl4, Cl5 and CL6 pipes- 201422 meter, 90 mm PVC Cl4- 47664 meter, 300 mm DI pipe- 400m, 250 mm DI pipe 900 meter Quantity of water to be produced : 19 MLD Expected annual revenue when project is completed:Rs 27740000 Ratio of material and labour: 60:40 Total cost of the project: Rs 1086980000 Source of funding: KIIFB
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 1086980000
AS Number wrd 004-02.apr-6/2019/kiifb
TS Amount (Rs) 1033500000
TS Number 5128/19-18,5127/19-20,5236/20-21,9135/20-21,17195/20-21
Total Bill Submitted (Rs) 557134014
Total Bill Paid (Rs) 557134014
Population Benefitted 59256
Capacity in MLD 19.00
Actual Project Completion Date 31 Dec 2022
Coverage kondotty muncipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB Kondotty-Package 2A- Construction of 14LL Capacity OHSR at Kumbalapara, supplying and laying pumping main from WTP to Kumbalapara, laying gravity mains to various reserviours, supply, errection and commiisioning of clear water pump set at WTP site Project Division Malappuram
2 KIIFB Kondotty-Package 2- Construction of 6LL Capacity OHSR at Chemmalaparamba, 8 LL Capacity OHSR Melengadi, Laying Transmission mains to various reserviours and distribution to zone 4 Melangadi Project Division Malappuram
3 KIIFB- Kondotty - Package 3 A- Laying distribution system for Zone 1,2 &3 and laying transmission main to various service reservoirs Project Division Malappuram
4 KIIFB Kondotty-Package 3B - Supply and laying distribution system to zone 5A,5B, 6 and 7 and Laying pumping main and gravity mains and distribution system to Cheruppady and Moochikundu zone, Project Division Malappuram
5 KIIFB Kondotty - Package I- construction of 19 MLD water treatment palnt- 600 mm DI K9 raw water pumping main - 270 HP VT raw wate pumpset Project Division Malappuram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Feb 2024 KIIFB Kondotty-Package 2- Construction of 6LL Capacity OHSR at Chemmalaparamba, 8 LL Capacity OHSR Melengadi, Laying Transmission mains to various reserviours and distribution to zone 4 Melangadi- OHSR work at Chemmelapparaba & Melangadi Structural work completed ,Finishing works progressing . Laying distribution work almost nearing completion. Pending PWD road works started. Road restoration and inter connection works are progressing. KIIFB Kondotty-Package 2A- Construction of 14LL Capacity OHSR at Kumbalapara, supplying and laying pumping main from WTP to Kumbalapara, laying gravity mains to various reserviours, supply, errection and commiisioning of clear water pump set at WTP site-14.00LL OHSR work completed , Laying 350mm pumping main for 14.60km completed KIIFB Kondotty - Package I- construction of 19 MLD water treatment palnt- 600 mm DI K9 raw water pumping main - 270 HP VT raw wate pumpset - Work completed-Commissioning work on going KIIFB Kondotty-Package 3B - Supply and laying distribution system to zone 5A,5B, 6 and 7 and Laying pumping main and gravity mains and distribution system to Cheruppady and Moochikundu zone- Work re tendered Malappuram Project Dn AE6
25 Oct 2023 Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing. Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- work completed package 3 B Work re tendered Malappuram Project Dn AE6
16 Sep 2023 Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing. Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- work completed package 3 B Work re tendered Malappuram Project Dn AE6
18 Aug 2023 work on going Malappuram Project Dn AE6
07 Aug 2023 Package 1 - structure work of 19 MLD wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR structure completed Charging pending,600mm Raw water pumping main work completed ,Electrical installation & Pumpset erection completed . Electrical inspectorate permission application for charging pending.8 LL OHSR at Melangadi Structural work completed, Finishing works progressing. Laying distribution work almost nearing completion stage a few roads pending due to local issues and want of PWD permission .Road restoration work progressing. Package 2A-14.00LL OHSR work completed, Laying 350mm pumping main for 14.0kmcompleted balance1.5Km pending due to PWD issues. It is expected to get permission in this month. Package 3A- work completed package 3 B Work re tendered Malappuram Project Dn AE6

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/04/2020
Scheduled date of Completion of the Project 31 Mar 2023
Expected date of Completion 31/03/2023

Processing Dates

AS Date 25 Jun 2019
TS Date 05 Nov 2019

Other details

Project Officers View