Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Jan 2022 |
package 1 - structure work of 19 MLT wtp completed, finishing work in progress, package 2- Chemmalaparamba 6 LL OHSR main slab completed, side wall in progress, 8 LL OHSR at Melangadi foudation work completed, all distribution pipe line supplied and 15 km PVC distribution pipe laid, package 2A-14 LL OHSR main slb work completed, 200mm DI gravity main fully supplied and 500 meter laid, 350 mm pumping main-9500 meter pipe supplied and 3000 meter laid. Package 3A- zone 1 and zone 2 pipe laying work completed and charged, zone 3 pipe laying work in progress, permission for laying pipe along NH966 is not obtained, package 3 B&C - the combined package for 3B and 3c is send for TS approval, overall 54 percentage of work completed |
Malappuram Project Dn AE6 |
|
03 Jan 2022 |
pipe laying work in progress overall 53 percentage of work completed |
Malappuram Project Dn AE6 |
|
01 Jan 2022 |
pipe laying work in progress overall 53 percentage of work completed |
Malappuram Project Dn AE6 |
|
21 Dec 2021 |
pipe laying work in progress overall 53 percentage of work completed |
Malappuram Project Dn AE6 |
|
01 Dec 2021 |
pipe laying work in progress overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
30 Nov 2021 |
pipe laying work in progress overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
22 Nov 2021 |
pipe laying work in progress overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
19 Nov 2021 |
pipe laying work in progress overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
18 Nov 2021 |
pipe laying work in progress overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
25 Sep 2021 |
package 1- 600mm DI K9 pipe 1306 meter supplied, 19 MLD WTP work 60 percent is completed,package 2- soil investigation for OHSR is completed, the design of OHSR is completed chammalaparamba ohsr work started , footing work in progress,80 pecentage of the pvc pipe is supplied package 2A- the soil investigation of OHSR site is completed and the design is completed and approved the footing work of the ohsr is n progress, ,package 3A-all PVC and GI pipe supplied- distribution network in zone 1 and 2 is completed zone 3 20 percentage is completed. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- tender approved, Package 3c- estimate under preparation after redesign |
Malappuram Project Dn AE6 |
|