Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Feb 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 55 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig Malappuram Project Dn AE6
17 Feb 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 55 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig Malappuram Project Dn AE6
09 Feb 2021 overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 55 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- estimate submitted for TS approval, Package 3c- estimate under preparation after redesig Malappuram Project Dn AE6
05 Feb 2021 overall 15 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 54 Km of distribution pipe laid. package 3B- estimate submitted for TS approval, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
25 Jan 2021 overall 14 percentage completed Malappuram Project Dn AE6
17 Dec 2020 overall 11 percentage completed Malappuram Project Dn AE6
12 Nov 2020 overall 10 percentage work completed Malappuram Project Dn AE6
30 Sep 2020 overall 8 percentage of work completed Malappuram Project Dn AE6
09 Sep 2020 overall 7 percentage of work completed Malappuram Project Dn AE6
15 Aug 2020 overall 6 percentage work completed, at prasent the Kondotty muncipal area is containment zone Malappuram Project Dn AE6