Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Feb 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 55 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig |
Malappuram Project Dn AE6 |
|
17 Feb 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 55 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe testing completed and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesig |
Malappuram Project Dn AE6 |
|
09 Feb 2021 |
overall 16 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 55 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe
testing completed and started pipe supply package 3B- estimate submitted for TS approval, Package 3c- estimate under preparation after redesig |
Malappuram Project Dn AE6 |
|
05 Feb 2021 |
overall 15 percentage of work completed, package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is started, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 54 Km of distribution pipe laid. package 3B- estimate submitted for TS approval, Package 3c- estimate under preparation after redesign |
Malappuram Project Dn AE6 |
|
25 Jan 2021 |
overall 14 percentage completed |
Malappuram Project Dn AE6 |
|
17 Dec 2020 |
overall 11 percentage completed |
Malappuram Project Dn AE6 |
|
12 Nov 2020 |
overall 10 percentage work completed |
Malappuram Project Dn AE6 |
|
30 Sep 2020 |
overall 8 percentage of work completed |
Malappuram Project Dn AE6 |
|
09 Sep 2020 |
overall 7 percentage of work completed |
Malappuram Project Dn AE6 |
|
15 Aug 2020 |
overall 6 percentage work completed, at prasent the Kondotty muncipal area is containment zone |
Malappuram Project Dn AE6 |
|