Status Date Overall Project Status Project Officer Contact
31 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 90%completed Palakkad Proj AE 3
30 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1185.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 90%completed Palakkad Proj AE 3
28 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 90%completed Palakkad Proj AE 3
27 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 90%completed Palakkad Proj AE 3
26 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 90%completed Palakkad Proj AE 3
26 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed Palakkad Proj AE 3
25 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed Palakkad Proj AE 3
24 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed Palakkad Proj AE 3
23 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed Palakkad Proj AE 3
21 May 2022 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed Palakkad Proj AE 3