| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 | |
| 19 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 | |
| 18 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 | |
| 16 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 | |
| 12 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 | |
| 11 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &1085.5m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 | |
| 10 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &755.85m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 | |
| 09 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &755.85m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 | |
| 06 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &755.85m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 | |
| 05 May 2022 | 3239.50 (out of 6635m)of 400mm DI K9 pipe recieved at site. &755.85m laying completed.Bhavani River crossing through the riverbed is going on. Finishing works of Intake well, Booster, WTP such as compound wall, plastering, painting, approach road in progress. 400KVA transformer-2no reached thesite. CFPS& VTPS to be supplied.over all 82%completed | Palakkad Proj AE 3 |