| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 18 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 17 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 16 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 12 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 11 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 started from booster to wtp. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 10 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 started from booster to wtp. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 09 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 started from booster to wtp. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 08 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 started from booster to wtp. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 06 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 pipe supplied. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 |