Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
18 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
17 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
16 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
12 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
11 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 started from booster to wtp. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
10 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 started from booster to wtp. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
09 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 started from booster to wtp. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
08 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 started from booster to wtp. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
06 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 pipe supplied. Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3