| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 09 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5023.35 m completed. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. 9 | Palakkad Project Dn EE | |
| 31 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 (930.1 m) from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 30 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 (930.1 m) from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Project Dn AE 4 | |
| 29 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 (930.1 m) from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 27 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 (930.1 m) from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 25 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 24 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 23 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 22 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 | |
| 20 Jan 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Proj AE 3 |