Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Feb 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5023.35 m completed. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. 9 Palakkad Project Dn EE
31 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 (930.1 m) from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
30 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 (930.1 m) from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Project Dn AE 4
29 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 (930.1 m) from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
27 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 (930.1 m) from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
25 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
24 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
23 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
22 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3
20 Jan 2024 Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -3525.85 m completed,balance laying of 400 mm DI K9 from booster to wtp is progressing. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. Palakkad Proj AE 3