| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, compound wall work on going. RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 | |
| 22 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 | |
| 21 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 | |
| 20 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 | |
| 19 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 | |
| 18 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 | |
| 16 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 | |
| 15 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 | |
| 14 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 | |
| 13 Dec 2023 | Intake well - All works completed. Booster Pump house- All works completed, RWPM -3525.85 m completed balance pipes to be supplied and laid by the contractor, Panchayath road restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. CC 8th and part bill worth 99Lakhs under scrutiny in this office. | Palakkad Proj AE 3 |