25 Feb 2021 The RWPM work started. Concrete work of Roof slab of Filter bed will completed today. The centering work and reinforcement work of base slab of Elembra tank is going on. The plastering work of Thadaparambu tank 60 % completed. The earth work of Sump at Cherani is started. Malappuram Project Dn AE2
15 Feb 2021 The work of RWPM and sump at Cherani are started. All other component except Section office are progressing. Section office work will starts soon. Malappuram Project Dn AE2
25 Jan 2021 Work is in progress Malappuram Project Dn AE2
21 Nov 2020 The Pipes for Raw water 700 mm dia has arrived. PWD handed over the road to KSTP and so, a meeting conducted by Edavanna MLA regarding permission from them. The structural work of Floculator, Filter bed, CW sump are in good progress. The foundation work of OHSR Thadaparambu is completed and the work is progressing The Earth work for OHSR Elembra (23.42 LL) - 90% completed. Design approved for CW Sump cum pump house Cherani. Malappuram Project Dn AE2
25 Oct 2020 The work of WTP is in good progress. The structural design of OH tanks, sump at Cheani are received and submitted for vetting. The 600 mm DI K9 pipe for RWPM arrived and laying work will starts after getting permission from KSTP. TS for Package 2 obtained Malappuram Project Dn AE2
16 Aug 2020 1.Hydraulic diagram of WTP confirmed by SE, detailed design to be submitted by the contract firm. 2. Site preparation works for wtp pressing at site 3. TS confirmation is awaited from KIIFB for further processing of the file Malappuram Project Dn AE2
16 Aug 2020 Earth leveling started. The TS from KIIFB is in pending Malappuram Project Dn AE2
19 Jun 2020 Earth leveling in WTP site started. Malappuram Project Dn AE2