Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Apr 2022 |
Package 1 -1) Manjeri section office building: - building construction work completed and Electrical work progressing. 2).Elambra OHSR:- Construction work completed and inlet and outlet pipe work completed, 3) Thadaparamba OHSR :- Construction work completed and inlet and outlet pipe work progressing,4) WTP :- Civil and Electrical work completed and SCADA work progressing at WTP, 5) Substation work at RWPH :- Plastering work completed at substation building at RWPH, and Transformer fixed 6) Cherani Sump cum clear water pump house – Civil work completed and clear water pump fixing work completed. 7) Raw water pumps:- Structural stability report of well cum pump house slab to be submitted to KIIFB before erection of raw water pumps. 8) Laying 700 mm DI raw water pumping main: - Additional length of 300 m pipe required to complete the work , variation estimate submitted for approval. Package 2 - Laying work of 400 mm DI pumping main from Cherani to Thadaparamba progressing (76%), Laying work of gravity main from Thadaparamba to Elambra progressing (56%), Laying pumping main from cherani sump to cherani OHSR progressing (90%)- PWD road cutting permission denied for laying pipe line in various roads due to various reasons |
Malappuram Project Dn AE2 |
|
16 Apr 2022 |
Package 1 -1) Manjeri section office building: - building construction work completed and Electrical work progressing. 2).Elambra OHSR:- Construction work completed and inlet and outlet pipe work progressing, 3) Thadaparamba OHSR :- Construction work completed and inlet and outlet pipe work progressing,4) WTP :- Civil and Electrical work completed and SCADA work progressing at WTP, 5) Substation work at RWPH :- Plastering work completed at substation building at RWPH, 6) Cherani Sump cum clear water pump house – Civil work completed and clear water pump fixing work progressing. 7) Raw water pumps:- Structural stability report of well cum pump house slab to be submitted to KIIFB before erection of raw water pumps. 8) Laying 700 mm DI raw water pumping main: - Additional length of 300 m pipe required to complete the work , variation estimate submitted for approval. Package 2 - Laying work of 400 mm DI pumping main from Cherani to Thadaparamba progressing (76%), Laying work of gravity main from Thadaparamba to Elambra progressing (56%), Laying pumping main from cherani sump to cherani OHSR progressing (30%)- PWD road cutting permission denied for laying pipe line in various roads due to various reasons |
Malappuram Project Dn AE2 |
|
06 Apr 2022 |
Package 1 -1) Manjeri section office building: - building construction work completed and Electrical work progressing. 2).Elambra OHSR:- Construction work completed and inlet and outlet pipe work progressing, 3) Thadaparamba OHSR :- Construction work completed and inlet and outlet pipe work progressing,4) WTP :- Civil and Electrical work completed and SCADA work progressing at WTP, 5) Substation work at RWPH :- Plastering work completed at substation building at RWPH, 6) Cherani Sump cum clear water pump house – Civil work completed and clear water pump fixing work progressing. 7) Raw water pumps:- Structural stability report of well cum pump slab to be submitted to KIIFB before erection of raw water pumps. 8) Laying 700 mm DI raw water pumping main: - Additional length of 300 m pipe required to complete the work , variation estimate submitted for approval.
Package 2 - Laying work of 400 mm DI pumping main from Cherani to Thadaparamba progressing (72%), Laying work of gravity main from Thadaparamba to Elambra progressing (56%), Laying pumping main from cherani sump to cherani OHSR progressing (16%)- PWD road cutting permission denied for laying pipe line in various roads due to various reasons
|
Malappuram Project Dn AE2 |
|
01 Apr 2022 |
Package 1 - Electrical work progressing at Manjeri section office building, Elambra OHSR inlet and outlet pipe work progressing, Thadaparamba OHSR inlet and outlet pipe work progressing, Electrical work completed and scada work progressing at WTP, Plastering work completed at substation building at RWPH, Cherani Sump cum clear water pump house - pump fixing work progressing. Structural stability report of well cum pump slab to be submitted to KIIFB before erection of raw water pumps. Package 2 - Laying work of 400 mm DI pumping main from Cherani to Thadaparamba progressing (72%), Laying work of gravity main from Thadaparamba to Elambra progressing (56%), Laying pumping main from cherani sump to cherani OHSR progressing (16%)- PWD road cutting permission denied for laying pipe line |
Malappuram Project Dn AE2 |
|
23 Mar 2022 |
Package 1 - Electrical work progressing at Manjeri section office building, Elambra OHSR inlet and outlet pipe work progressing, Thadaparamba OHSR inlet and outlet pipe work progressing, Electrical and scada work progressing at WTP, Plastering work progressing at substation building at RWPH, Cherani Sump cum clear water pump house - pump fixing work progressing. Package 2- Laying work of 400 mm DI pumping main from Cherani sump to Thadaparamba OHSR progressing (60%), Laying work of gravity main from Thadaparamba OHSR to Elambra OHSR progressing (40%), Laying of pumping main from Cherani sump to Cherani OHSR prograssing (10%) |
Malappuram Project Dn AE2 |
|
10 Mar 2022 |
Package 1 - Electrical work progressing at Manjeri section office building, Elambra OHSR inlet and outlet pipe work progressing, Thadaparamba OHSR inlet and outlet pipe work progressing, Electricaland scada work progressing at WTP, Plastering work progressing at substation building at RWPH, Cherani Sump cum clear water pump house - pump fixing work progressing.
Package 2- Laying work of 400 mm DI pumping main from Cherani to Thadaparamba progressing (50%), Laying work of gravity main from Thadaparamba to Elambra progressing (40%) |
Malappuram Project Dn AE2 |
|
02 Mar 2022 |
Electrical work progressing at Manjeri section office building, Compound wall progressing for Elambra OHSR, Pipe work progressing for Thadaparamba OHSR, Electricaland scada work progressing at WTP, Plastering work progressing at substation building at RWPH, Laying work of 400 mm DI pumping main from Cherani to Thadaparamba progressing (50%), Laying work of gravity main from Thadaparamba to Elambra progressing (40% |
Malappuram Project Dn AE2 |
|
21 Feb 2022 |
Tiles work progressing at Manjeri section office building, Compound wall progressing for Elambra OHSR, Pipe work progressing for Thadaparamba OHSR, Electrical work progressing at WTP, roof slab completed at substation building at RWPH, Laying work of 400 mm DI pumping main from Cherani to Thadaparamba progressing (45%), Laying work of gravity main from Thadaparamba to Elambra progressing (40% |
Malappuram Project Dn AE2 |
|
14 Feb 2022 |
Tiles work progressing at Manjeri section office building, Compound wall progressing for Elambra OHSR, Pipe work progressing for Thadaparamba OHSR, Electrical work progressing at WTP, roof slab completed at substation building at RWPH, Laying work of 400 mm DI pumping main from Cherani to Thadaparamba progressing (45%), Laying work of gravity main from Thadaparamba to Elambra progressing (40%) |
Malappuram Project Dn AE2 |
|
07 Feb 2022 |
Tiles work progressing at Manjeri section office building, Compound wall progressing for Elambra OHSR, Pipe work progressing for Thadaparamba OHSR, Electrical work progressing at WTP, Shuttering work progressing for roof slab at substation building at RWPH, Laying work of 400 mm DI pumping main from Cherani to Thadaparamba progressing |
Malappuram Project Dn AE2 |
|