Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Jul 2024 Package 1 - Completed and Commissioned; Package 2 - 400mm pumping main, 400 mm gravity main and 600mm pumping main completed and commissioned Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( no progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line.100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes , in high court. KIIFB decision to be obtained for finalizing the short closing of package 2of the work Malappuram Project Dn
10 Jul 2024 Package 1 - Completed and Commissioned; Package 2 - 400mm pumping main, 400 mm gravity main and 600mm pumping main completed and commissioned Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( no progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line.100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes , in high court. KIIFB decision to be obtained for finalizing the short closing of package 2of the work Malappuram Project Dn AE2
26 Jun 2024 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( no progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line.100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes , in high court. KIIFB decision to be obtained for finalizing the short closing of package 2of the work Malappuram Project Dn AE2
10 Jan 2024 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( slow progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line.100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes , in high court. KIIFB decision to be obtained for finalizing the short closing of package 2of the work Malappuram Project Dn AE2
02 Jan 2024 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( slow progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line.100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes , in high cour Malappuram Project Dn AE2
14 Nov 2023 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( slow progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line.100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes , in high court Malappuram Project Dn AE2
08 Nov 2023 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( slow progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line. Malappuram Project Dn AE2
23 May 2023 Commissioning of production components pending due non availability of fund for deposition to KSEB. Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in KSEB Power connection in Areekode and Cherani Pump house are pending Package 2 :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR progressing (98%), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line Malappuram Project Dn AE2
04 May 2023 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in KSEB Power connection in Areekode and Cherani Pump house are pending Package 2 :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR progressing (98%), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line Malappuram Project Dn AE2
11 Apr 2023 Package 1 :- Power Connection/ Contract demand Enhancement Pending for Commissioning. Work completed.- 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in KSEB Power connection in Areekode and Cherani Pump house are pending Package 2 :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR progressing (98%), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line Malappuram Project Dn AE2