Status Date Overall Project Status Project Officer Contact
31 May 2021 1. The Structural works of WTP Areacode Completed. Masonry and plastering works in progress 2. RWPM 1780 m out of 2330 had completed. 3. Setting out completed for substation at RW Pumping station. 4. Second lift of side wall of Sump Cherani Completed. 6. Plastering work of OHST Thadaparamba Completed. 7. Roof slab casted at OHSR Elembra. The speed of whole work affected by restrictions of Lock down due to spread of covid 19 Malappuram Project Dn AE2
21 Apr 2021 For Package 1- 1. Structural work of all items except Aerator completed at WTP site. 2) 700 mm DI K9 RWPM pipe laying work started after the Election restriction (600m out of 2330m laid. 3) Structural work of 4.72LL OHSR at Thadapparamba completed 4) 3rd list side wall concrete of 23.4 LL OHSR at Elambra in progress 5) Base slab concrete of 5LL CW Sump cum booster station at Cherani in progress Package-II :- various diameter DI pipes 150/250/350/600mm reached at site after factory test. Laying work being started at site Malappuram Project Dn AE2
21 Apr 2021 Package -1 in progress - overall 50%+ Malappuram Project Dn AE2
14 Apr 2021 For Package 1, Structural work of all items except Aerator completed at WTP. 700 mm DI K9 pipe laying work started after the Election ban by District Collector. Interlinking work, Compound wall and painting work work are to be completed to Thadaparamabu tank. For Elembra tank, Centering work of last lift of side wall progressing. The DI pipes are arriving for laying Distribution system in Package 2 Malappuram Project Dn AE2
31 Mar 2021 All ongoing works in package 1 in progress. In Package 2, 250 mm & 200 mm DI pipes arrived at site for laying distribution system. Malappuram Project Dn AE2
09 Mar 2021 All ongoing works in this package are in progress. The agreement for package 2 executed and supply order placed for pipes and expect arrived soon Malappuram Project Dn AE2
07 Mar 2021 All ongoing works in this package are progress. The agreement for package 2 executed and supply order placed for pipes Malappuram Project Dn AE2
04 Mar 2021 All ongoing works in this package are progress. The agreement for package 2 executed Malappuram Project Dn AE2
01 Mar 2021 Filter bed roof and wash water tank bottom slab etc are completed in WTP. plastering work in progress at WTP site and OHSR Thadaparambu. Reinforcement work of Elembra tank started. Laying 700 mm DI K9 RWPM in Progress. Malappuram Project Dn AE2
26 Feb 2021 Raw RWPM in progress. Malappuram Project Dn AE2