Status Date |
Overall Project Status |
Project Officer |
Contact |
16 Nov 2021 |
RWPH substation building foundation work completed, WTP tiles fixing work progressing, clarifier plate fixing work progressing, Manjeri office building plastering work progressing |
Malappuram Project Dn AE2 |
|
08 Nov 2021 |
WTP - filter media filling completed, elctromechanical work progressing, agitator fixed in flocculator and flash mixer, scraper work in clarifier progressing, tiles and hand rails fixed Manjeri section office building - structural completed, bricks work progressing Cherani sump cum pump house - finishing work progressing Thadaparamba OHSR and Elembra OHS- Finishing work progressing |
Malappuram Project Dn AE2 |
|
05 Nov 2021 |
WTP - filter media filling completed, elctromechanical work progressing, agitator fixed in flocculator and flash mixer, scraper work in clarifier progressing, tiles and hand rails fixed Manjeri section office building - structural completed, bricks work progressing Cherani sump cum pump house - finishing work progressing Thadaparamba OHSR and Elembra OHS- Finishing work progressing |
Malappuram Project Dn AE2 |
|
01 Nov 2021 |
Bricks work at manjeri office building and electromechanical work at WTP progressing |
Malappuram Project Dn AE2 |
|
25 Oct 2021 |
Bricks work at manjeri office building, footing and column work at substation building at RWPH, tile fixing work and electro mechanical work at WTP progressing |
Malappuram Project Dn AE2 |
|
20 Oct 2021 |
Bricks work at manjeri office building, electromechanical work at WTP, footing work for sub station building at RWPH are progressing |
Malappuram Project Dn AE2 |
|
11 Oct 2021 |
Electromechanical work at WTP, boundary wall at Thadaparamba OHSR, cement plastering work at cherani sump and Manjeri section office Progressing |
Malappuram Project Dn AE2 |
|
27 Sep 2021 |
construction work of panel room and shift room at RWPH started |
Malappuram Project Dn AE2 |
|
25 Sep 2021 |
Electromechanical work at WTP progressing |
Malappuram Project Dn AE2 |
|
20 Sep 2021 |
Electromechanical work at WTP Progressing |
Malappuram Project Dn AE2 |
|