Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Budget 2017-18 KIIFB- Tranche - 10 - WRD 025- 25 Manjeri Suburban Drinking Water Project

Project Budget 2017-18 KIIFB- Tranche - 10 - WRD 025- 25 Manjeri Suburban Drinking Water Project
Project Code MLPKIIFB1118517
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description BUDGET 2018-20 TRAN - 10 - WRD-025-25- Manjeri Suburban Drinking Water Project Improvements and augmentation of UWSS to Manjeri including water supply arrnagements to Payyanad and Thadaparambu area of Manjeri Municipality Intake well- Existing well at Areacode Pumping System – 188 HP VT pump set – 2 Nos Transmission lines – CWPM – 400 mm DI – 3760m, CWGM - 400 mm DI – 4230 m Water Treatment plant – 19 mld Capacity – Plate settler type OH tanks – 4.72 LL at Thadaparambu, 23.42 LL at Elembra GL Tanks – Nil Supply lines – 400 mm DI to 150 mm DI – 14480 m 160 mm PVC ( Inc rider main)- 92278m 110 mm PVC ( For parallel line to DI ) – 14280 Qty of water produced - 19 Mld Expected Annual Revenue - Rs 2.22 Crores Total cost of Project – 74.50 Crore Source of funding – KIIFB Date of AS - 27-03-2018 Date of T S - Pkg 1 – 12-12-2019, Pkg 2 – 13-10-2020 Date of Tender Pkg 1 – 13-10-2020 Pkg 2 – Date of awarding work – Pkg 1 - 06-03-2020 Date of Signing Agreement Pkg 1 – 16-03-2020 Scheduled time of completion - Pkg 1 – 30-07-2022 Officer now responsible for execution AE – Praveen P B. , AEE –Afsal F, EE – Ansar M S
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 725800000
AS Number G.O(Rt)No. 209/2018/WRD
TS Amount (Rs) 711500000
TS Number TS/2019-2020/2019/20201 Dated: 12-12-2019, . TS/2020-2021/2020/20180 Dated: 13-10-2020
Total Bill Submitted (Rs) 343669607
Total Bill Paid (Rs) 343669607
Population Benefitted 158530
Capacity in MLD 19.00
Actual Project Completion Date 31 Mar 2024
Coverage Eastern side of Manjeri payyanad and Thadaparambu area and improvement of existing distribution system
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 BUDGET 2017 - 18 - KIIFB: Tran-10-WRD-025-25-MANJERI SUBURBAN DRINKING WATER PROJECT IMPROVEMENTSAND AUGMENTATION OF UWSS TO MANJERIMUNICIPALITY INCLUDING WATER SUPPLYARRANGEMENTS TO PAYYANADAND THADAPPARAMBA AREA OF MANJERI MUNICIPALITY, MALAPPURAM DISTRICT- Package-I Project Division Malappuram
2 BUDGET 2017 - 18 - KIIFB: Tran-10-WRD-025-25-MANJERI SUBURBAN DRINKING WATER PROJECT IMPROVEMENTSAND AUGMENTATION OF UWSS TO MANJERIMUNICIPALITY INCLUDING WATER SUPPLYARRANGEMENTS TO PAYYANADAND THADAPPARAMBA AREA OF MANJERI MUNICIPALITY, MALAPPURAM DISTRICT- Pkg2- Distribution system Project Division Malappuram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Jan 2024 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( slow progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line.100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes , in high court. KIIFB decision to be obtained for finalizing the short closing of package 2of the work Malappuram Project Dn AE2
02 Jan 2024 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( slow progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line.100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes , in high cour Malappuram Project Dn AE2
14 Nov 2023 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( slow progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line.100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes , in high court Malappuram Project Dn AE2
08 Nov 2023 Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in existing KSEB Power connection in Areekode and Cherani Pump house are pending. Package 2( slow progress) :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line. Malappuram Project Dn AE2
23 May 2023 Commissioning of production components pending due non availability of fund for deposition to KSEB. Package 1 :- Work Completed, Power Connection/ Contract demand Enhancement Pending for Commissioning. - 1) Manjeri section office building. 2).Elambra OHSR, 3) Thadaparamba OHSR :- 4) WTP 5) Substation and Transformer 6) Cherani Sump cum clear water pump house 7) Raw water pumpsets 8) Laying 700 mm DI raw water pumping main etc are completed. Enhancement of contract demand in KSEB Power connection in Areekode and Cherani Pump house are pending Package 2 :- 1).Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR progressing (98%), 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line Malappuram Project Dn AE2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 14/06/2020
Scheduled date of Completion of the Project 24 Jun 2023
Expected date of Completion 31/03/2024

Processing Dates

AS Date 27 Mar 2018
TS Date 12 Dec 2019

Other details

Project Officers View