Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Sep 2021 |
Electro mechanical work at Areekode WTP progressing, office building work at Manjeri progressing |
Malappuram Project Dn AE2 |
|
13 Sep 2021 |
Works at WTP, section office, Cherani sump are progressing, Section office roof slab concrete completed |
Malappuram Project Dn AE2 |
|
08 Sep 2021 |
Works at WTP, section office, Cherani sump are progressing |
Malappuram Project Dn AE2 |
|
31 Aug 2021 |
In Package 1, Site clearance and setting out of the substation building done and work starts soon. Laying 700 mm DI pipe completed 222m along PWD road and KWA pipe line road. The report of surge analysis of the RWPM is to be obtained from contractor. 90% civil works completed at WTP. The Electro mechanical works, Electrical wiring, fitting door/ windows etc. are in progress. At Cherani, Roof slab concrete completed . Plastering work of Elembra tank on going and 60% completed. The tank testing to be conducted. Ground floor slab and second floor columns of Section office building completed, shuttering work of Roof slab is in progress. The compound wall and interlinking works at Elembra and Thadaparamba tank is remaining.
In Package 2, DI pipes 150 mm to 600 mm supplied. The bill prepared and submitted. The PWD officers denied to issue the permission for digging PWD road stating the Monsoon ban. |
Malappuram Project Dn AE2 |
|
24 Aug 2021 |
In Package 1, Site clearance and setting out of the substation building done and work starts soon. Laying 700 mm DI pipe completed along PWD road and KWA pipe line road. The report of surge analysis of the RWPM is to be obtained from contractor. 90% civil works completed at WTP. The Electro mechanical works, Electrical wiring, fitting door/ windows etc. are in progress. At Cherani, Roof slab concrete completed . Plastering work of Elembra tank on going and 60% completed. The tank testing to be conducted. Ground floor slab of Section office building completed and second floor columns in progress. The compound wall and interlinking works at Elembra and Thadaparamba tank is remaining.
In Package 2, DI pipes 150 mm to 600 mm supplied. The bill prepared and submitted. The PWD officers denied to issue the permission for digging PWD road stating the Monsoon ban. |
Malappuram Project Dn AE2 |
|
26 Jul 2021 |
Works at WTP, section office, Cherani sump are progressing. Quality wing of KIIFB team conducted tests at Elembra tank site. |
Malappuram Project Dn AE2 |
|
19 Jul 2021 |
Package I. 1. Site leveling completed for sub station building at Intake. -2. Electro mechanical work and Electrification works progressing in WTP. 3. 85% work completed the work of RWPM. 4. Column work and masonry work progressing at Sump Cherani.5. All work except inter linking and compound wall completed at Thadaparamba OHSR. 6. Plastering work completed at GF of OHSR Elembra. 7. Ground floor colmns of section office is progressing.
Heavy rain in Manjeri and Areacod, which interrupting the works. |
Malappuram Project Dn AE2 |
|
08 Jul 2021 |
A Routine Examination of GCW, KIIFB conducted the works include in Package I |
Malappuram Project Dn AE2 |
|
16 Jun 2021 |
Package-1 - The WTP/OHSR main structural works almost completed. Section office and substation building works under progress. RWPM 80% completed
Package-II - DI pipes supplied by the contractor and laying work partially started |
Malappuram Project Dn AE2 |
|
10 Jun 2021 |
1. Masonry and plastering works progressing. Initiative being taken to start electro mechanical works. Pipe connectors of WTP supplied. 2. RWPM 1820 m out of 2330 had completed. The trench met hard rock in KSTP road 3. Setting out completed for substation at RW Pumping station. 4. S side wall concreting of Sump Cherani Completed. 6. Plastering work of OHST Thadaparamba Completed. 7. Roof slab casted at OHSR Elembra. The speed of whole work affected by restrictions of Lock down. 8. The site levelling for section office building Manjeri Completed |
Malappuram Project Dn AE2 |
|