Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 May 2021 Work in progress | 10% Completed | 27/05/2021 9% of work complete Total 42.860 km pipe laid 90mm pvc pipe -8kg-12498 m supplied and 12895.00m laid 90mm pvc 6kg- 15898 m supplied and 18433.40 m laid 90mm pvc 10 kg-2751.00m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1761.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-322,Pattenchery-58 Nos total 381.00 nos of FHTC provided Chittur Project Dn - AE 1
25 May 2021 Work in progress | 9% Completed | 25/05/2021 9% of work complete Total 42.760 km pipe laid 90mm pvc pipe -8kg-12398 m supplied and 12895.00m laid 90mm pvc 6kg- 15898 m supplied and 18433.40 m laid 90mm pvc 10 kg-2751.00m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1761.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-322,Pattenchery-58 Nos total 381.00 nos of FHTC provided Chittur Project Dn - AE 1
19 May 2021 9% of work complete Total 42.660 km pipe laid 90mm pvc pipe -8kg-12298 m supplied and 12895.00m laid 90mm pvc 6kg- 15898 m supplied and 18433.40 m laid 90mm pvc 10 kg-2751.00m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1761.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-322,Pattenchery-58 Nos total 381.00 nos of FHTC provided Chittur Project Dn - AE 1
13 May 2021 9% of work complete Total 42.660 km pipe laid 90mm pvc pipe -8kg-12298 m supplied and 12895.00m laid 90mm pvc 6kg- 15898 m supplied and 18433.40 m laid 90mm pvc 10 kg-2751.00m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1761.60m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 3908 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-833.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-322,Pattenchery-58 Nos total 381.00 nos of FHTC provided Chittur Project Dn - AE 1
11 May 2021 Total 26.3755 km pipe laid 90mm pvc pipe -8kg-12298 m supplied and 5772.00m laid 90mm pvc 6kg- 15898 m supplied and 13619.40 m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1650m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 2242 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-815.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-346,Pattenchery-34 Nos total 381.00 nos of FHTC provided Chittur Project Dn - AE 1
29 Apr 2021 Total 26.1755 km pipe laid 90mm pvc pipe -8kg-12198 m supplied and 5772.00m laid 90mm pvc 6kg- 15798 m supplied and 13619.40 m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1650m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 2242 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-815.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-346,Pattenchery-34 Nos total 381.00 nos of FHTC provided Chittur Project Dn - AE 1
26 Apr 2021 Total 26.1755 km pipe laid 90mm pvc pipe -8kg-12198 m supplied and 5772.00m laid 90mm pvc 6kg- 15798 m supplied and 13619.40 m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1650m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 2242 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-815.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-295,Pattenchery-34 Nos total 330.00 nos of FHTC provided Chittur Project Dn - AE 1
20 Apr 2021 Work in progress | 7% Completed | 20/04/2021 Total 25.8755 km pipe laid 90mm pvc pipe -8kg-12198 m supplied and 5572.00m laid 90mm pvc 6kg- 15798 m supplied and 13519.40 m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1650m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 2242 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-815.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-263,Pattenchery-34 Nos total 298 nosof FHTC provided Chittur Project Dn - AE 1
19 Apr 2021 Work in progress | 7% Completed | 19/04/2021 Total 25.8755 km pipe laid 90mm pvc pipe -8kg-12198 m supplied and 5572.00m laid 90mm pvc 6kg- 15798 m supplied and 13519.40 m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1650m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 2242 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-815.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-263,Pattenchery-34 Nos total 298 nosof FHTC provided Chittur Project Dn - AE 1
13 Apr 2021 Work in progress | 7% Completed | 13/04/2021 Total 25.6755 km pipe laid 90mm pvc pipe -8kg-12198 m supplied and 5472.00m laid 90mm pvc 6kg- 15798 m supplied and 13519.40 m laid 500mm DI-K9 pipe-250m supplied and 165.00 m laid 450mm DI - 1650 m supplied and 1650m laid 350mm DI- 1562 m supplied and 811 m laid 250mm DI-27.50M laid 20 mm pvc 12.50 kg 1998 m supplied 110mm pvc 6 kg-3000m supplied - 1074 m laid 160mm pvc 6 kg-3000m supplied and 2142 m laid 140mm pvc-6 kg-3000m supplied 160mm pvc -10kg-815.50m laid FHTC provided Total Nallepilly-1 No, Perumatty No.-239,Pattenchery-34 Nos total 274 nosof FHTC provided Chittur Project Dn - AE 1