Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Jun 2021 | Waiting for permission from railway.a thrust force report is required. Submitted requst for the report to GCE kannur.Due to absence of concerned experts in college due to lock down.Contacted yesterday also. | Koothuparamba Proj AE 2 | |
19 Jun 2021 | Waiting for permission from railway | Koothuparamba Proj AE 2 | |
13 Jun 2021 | Waiting for permission from Railway | Koothuparamba Proj AE 2 | |
10 Jun 2021 | Railway line crossing permission is pending. Contacted Divisional Railway Engineer Palakkad.Asked to submit design calculation of desighn calculation and thrust bed details including jacking force required to overcome soil resistance. Then requsted to GCE Kannur.The report is not received due to lock down. | Koothuparamba Proj AE 2 | |
19 Apr 2021 | Railway crossing permission to be obtained | Koothuparamba Proj AE 2 | |
02 Feb 2021 | Railway crossing permission to be obtained | Koothuparamba Proj AE 2 | |
30 Jan 2021 | Work completed and trial run started except Railway crossing work pending.Waiting for permission. | Koothuparamba Proj AE 2 | |
16 Nov 2020 | 98% completed | Koothuparamba Proj AE 2 | |
14 Sep 2020 | work completed except a Railway crossing | Koothuparamba Proj AE 2 |