| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 May 2022 | work completed on 14/03/22.Final bill paid. | Koothuparamba Proj AE 2 | |
| 22 Apr 2022 | work completed on 14/03/22.Final bill submitted | Koothuparamba Proj AE 2 | |
| 17 Mar 2022 | work completed.Final bill submitted | Koothuparamba Proj AE 2 | |
| 14 Mar 2022 | Railway crossing work completed.Trial running started. | Koothuparamba Proj AE 2 | |
| 10 Mar 2022 | Railway crossing by Push through method in progress. | Koothuparamba Proj AE 2 | |
| 06 Mar 2022 | Railway crossing by Push through method in progress. | Koothuparamba Proj AE 2 | |
| 02 Mar 2022 | Railway crossing by Push through method started .But slow progress due to sobsoil water | Koothuparamba Proj AE 2 | |
| 27 Feb 2022 | Railway crossing by Push through method started .But slow progress due to sobsoil water | Koothuparamba Proj AE 2 | |
| 24 Feb 2022 | Railway crossing by Push through method started but slow progress due to sub soil water | Koothuparamba Proj AE 2 | |
| 21 Feb 2022 | Railway crossing by Push through method started but slow progress due to sub soil water | Koothuparamba Proj AE 2 |