Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 May 2022 | work completed on 14/03/22.Final bill paid. | Koothuparamba Proj AE 2 | |
22 Apr 2022 | work completed on 14/03/22.Final bill submitted | Koothuparamba Proj AE 2 | |
17 Mar 2022 | work completed.Final bill submitted | Koothuparamba Proj AE 2 | |
14 Mar 2022 | Railway crossing work completed.Trial running started. | Koothuparamba Proj AE 2 | |
10 Mar 2022 | Railway crossing by Push through method in progress. | Koothuparamba Proj AE 2 | |
06 Mar 2022 | Railway crossing by Push through method in progress. | Koothuparamba Proj AE 2 | |
02 Mar 2022 | Railway crossing by Push through method started .But slow progress due to sobsoil water | Koothuparamba Proj AE 2 | |
27 Feb 2022 | Railway crossing by Push through method started .But slow progress due to sobsoil water | Koothuparamba Proj AE 2 | |
24 Feb 2022 | Railway crossing by Push through method started but slow progress due to sub soil water | Koothuparamba Proj AE 2 | |
21 Feb 2022 | Railway crossing by Push through method started but slow progress due to sub soil water | Koothuparamba Proj AE 2 |