Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Nov 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work. | Koothuparamba Proj AE 2 | |
04 Nov 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work. | Koothuparamba Proj AE 2 | |
02 Nov 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work. | Koothuparamba Proj AE 2 | |
31 Oct 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work. | Koothuparamba Proj AE 2 | |
29 Oct 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work. | Koothuparamba Proj AE 2 | |
27 Oct 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work. | Koothuparamba Proj AE 2 | |
25 Oct 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work. | Koothuparamba Proj AE 2 | |
21 Oct 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work. | Koothuparamba Proj AE 2 | |
19 Oct 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway | Koothuparamba Proj AE 2 | |
16 Oct 2021 | Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway | Koothuparamba Proj AE 2 |