| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Aug 2021 | Rail crossing permission pending. | Koothuparamba Proj AE 2 | |
| 11 Aug 2021 | Rail crossing permission pending | Koothuparamba Proj AE 2 | |
| 08 Aug 2021 | rail crossing work pending | Koothuparamba Proj AE 2 | |
| 05 Aug 2021 | Rail crossing permission pending | Koothuparamba Proj AE 2 | |
| 03 Aug 2021 | Rail crossing permission pending. | Koothuparamba Proj AE 2 | |
| 01 Aug 2021 | Rail crossing permission pending | Koothuparamba Proj AE 2 | |
| 30 Jul 2021 | Rail crossing permission pending. Report from GCE kannur is not yet received. Today went to GCE kannur and enquired about the report. They informed as the report is under preperation. | Koothuparamba Proj AE 2 | |
| 28 Jul 2021 | Rail crossing permission not received | Koothuparamba Proj AE 2 | |
| 26 Jul 2021 | rail crossing permission pending | Koothuparamba Proj AE 2 | |
| 25 Jul 2021 | Rail crossing permission pending | Koothuparamba Proj AE 2 |