13 Oct 2021 Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway Koothuparamba Proj AE 2
11 Oct 2021 ail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway Koothuparamba Proj AE 2
09 Oct 2021 Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway Koothuparamba Proj AE 2
04 Oct 2021 Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway Koothuparamba Proj AE 2
30 Sep 2021 Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway Koothuparamba Proj AE 2
28 Sep 2021 Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway Koothuparamba Proj AE 2
25 Sep 2021 Rail crossing permission obtained.Letter issued to the contractor concerned to start the work. Koothuparamba Proj AE 2
22 Sep 2021 Rail crossing permission obtained.Letter issued to the contractor concerned to start the work. Koothuparamba Proj AE 2
20 Sep 2021 Rail crossing permission obtained.Letter issued to the contractor concerned to start the work. Koothuparamba Proj AE 2
16 Sep 2021 Rail crossing permission obtained.Letter issued to the contractor concerned to start the work. Koothuparamba Proj AE 2