Status Date Overall Project Status Project Officer Contact
05 Jul 2021 rail crossing permission pending Koothuparamba Proj AE 2
03 Jul 2021 Rail crossing permission pending Koothuparamba Proj AE 2
02 Jul 2021 Rail crossing permission pending Koothuparamba Proj AE 2
01 Jul 2021 Railway crossing permission is pending.A report regarding Jackforce is requested to GCE kannur.Contacted today also with GCE Kannur.Expecting the report next week. Koothuparamba Proj AE 2
30 Jun 2021 Permission for railway crossing is pending. Koothuparamba Proj AE 2
29 Jun 2021 Report of thrust force from GCE kannur is not yet received.Contacted today also with GCE kannur.Concerned experts are not reached at college due to lockdown. Koothuparamba Proj AE 2
29 Jun 2021 Waiting for rail crossing permission. Koothuparamba Proj AE 2
28 Jun 2021 Waiting for rail crossing permission.Report about thrust force calculation is pending with GCE kannur.Contacting daily.Delay is due to LOCK down. Koothuparamba Proj AE 2
24 Jun 2021 waiting for rail crossing permission Koothuparamba Proj AE 2
23 Jun 2021 Waiting for permission from railway Koothuparamba Proj AE 2